x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is 
  • a)
    6
  • b)
    10
  • c)
    12
  • d)
    15
  • e)
    None of these 
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
x number of men can finish a piece of work in 30 days. If there were 6...
View all questions of this test
Most Upvoted Answer
x number of men can finish a piece of work in 30 days. If there were 6...
Given:
- x men can finish a piece of work in 30 days.
- If there were 6 men more, the work could be finished in 10 days less.

To find:
- The original number of men.

Solution:

Let's assume the original number of men is 'n'.

Step 1: Determining the work rate
- In 30 days, x men can complete the work.
- Therefore, the work rate of x men is 1/30 per day.
- Let's calculate the work rate of 1 man per day, which would be (1/30) / x = 1/(30x).

Step 2: Determining the new work rate
- If there were 6 men more, the work could be finished in 10 days less.
- This means that (n + 6) men can complete the work in 30 - 10 = 20 days.
- Therefore, the work rate of (n + 6) men is 1/20 per day.
- Let's calculate the work rate of 1 man per day, which would be (1/20) / (n + 6) = 1/(20(n + 6)).

Step 3: Equating the work rates
- Since the work done by both groups of men is the same, the work rates can be equated.
- 1/(30x) = 1/(20(n + 6))

Step 4: Solving the equation
- To simplify the equation, we can cross-multiply.
- 20(n + 6) = 30x
- Simplifying further, we get:
- 20n + 120 = 30x
- 20n = 30x - 120
- 2n = 3x - 12

Step 5: Substituting values to find the original number of men
- Since the answer options are given in terms of individual men, we can substitute some values to find the original number of men.
- Let's try n = 12:
- 2(12) = 3x - 12
- 24 = 3x - 12
- 36 = 3x
- x = 12

- Therefore, the original number of men is 12.

Hence, the correct answer is option 'C' (12).
Explore Courses for Banking Exams exam
x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer?
Question Description
x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer? for Banking Exams 2025 is part of Banking Exams preparation. The Question and answers have been prepared according to the Banking Exams exam syllabus. Information about x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Banking Exams 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer?.
Solutions for x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Banking Exams. Download more important topics, notes, lectures and mock test series for Banking Exams Exam by signing up for free.
Here you can find the meaning of x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice x number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men isa)6b)10c)12d)15e)None of theseCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Banking Exams tests.
Explore Courses for Banking Exams exam

Top Courses for Banking Exams

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev