The main factor to be considered while preparing a detailed estimate is
  • a)
    Quantity of materials
  • b)
    Availability of materials
  • c)
    Transportation of materials
  • d)
    All of the above
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
The main factor to be considered while preparing a detailed estimate i...
The preparations of a detailed construction estimate consist of working out quantities of various items of work and then determine the cost of each item. This is prepared in two stages.
1. Details of measurements and calculation of quantities
2. Abstract of Estimated Cost
In the first stage, the quantity, availability, and transportation of materials parameters is being analyzed.
In the second stage, the total abstract of the above analysis is shown.
View all questions of this test
Most Upvoted Answer
The main factor to be considered while preparing a detailed estimate i...
The main factor to be considered while preparing a detailed estimate is:

Quantity of materials:
- The quantity of materials required for a project plays a crucial role in estimating the cost.
- Estimators need to determine the accurate quantity of materials needed for various construction activities such as excavation, concrete work, masonry, plastering, etc.
- This helps in calculating the cost of materials and ensures that there are no shortages or excess materials, which can impact the overall project budget.

Availability of materials:
- The availability of materials is another important factor to consider while preparing a detailed estimate.
- Estimators need to assess the availability of materials in the local market or nearby suppliers.
- If certain materials are not readily available, alternative sources may need to be considered, which can affect the overall cost estimation.
- Additionally, the cost of materials may vary depending on their availability and market conditions.

Transportation of materials:
- The transportation of materials from the supplier to the construction site is a significant aspect of cost estimation.
- Estimators need to consider the distance between the supplier and the site, as well as the mode of transportation (e.g., truck, rail, etc.) and associated costs.
- Transportation costs can vary depending on factors such as fuel prices, labor charges, and road conditions.
- Estimators should also factor in any additional costs related to handling and unloading materials at the site.

All of the above:
- Considering all the factors mentioned above is essential for preparing an accurate and detailed estimate.
- The quantity of materials determines the overall cost of materials, while the availability of materials affects their procurement and cost.
- Transportation costs need to be included to ensure an accurate estimation of the overall project cost.
- Neglecting any of these factors can lead to cost overruns, delays, or even project failure.
- Therefore, it is crucial for estimators to take into account the quantity, availability, and transportation of materials while preparing a detailed estimate.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer?
Question Description
The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer?.
Solutions for The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The main factor to be considered while preparing a detailed estimate isa)Quantity of materialsb)Availability of materialsc)Transportation of materialsd)All of the aboveCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev