Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  The load factors for live and dead load are t... Start Learning for Free
The load factors for live and dead load are taken respectively as:

  • a)
    1.5 and 2.2

  • b)
    2.2 and 1.5 

  • c)
    1.5 and 1.5

  • d)
    2.2 and 2.2

Correct answer is option 'C'. Can you explain this answer?
Verified Answer
The load factors for live and dead load are taken respectively as:a)1....
The load factors for live load and dead load shall be taken as 1.5 and 1.5 respectively.
IS 456:2000 (page no 68 table no 18)
"For the limit states of serviceability the values of Y1, given in this table are applicable for short-term effects. While assessing the long-term effects due to creep the dead load and that part of the live load likely to be permanent may only be considered."
View all questions of this test
Most Upvoted Answer
The load factors for live and dead load are taken respectively as:a)1....
Load Factors for Live and Dead Load in Civil Engineering

In the design of structures, it is important to consider the loads that the structure will be subjected to. The loads can be classified as live loads and dead loads. Live loads are the loads that are temporary and can change in magnitude and location, whereas dead loads are the loads that are permanent and remain constant throughout the life of the structure. Load factors are used to account for uncertainties and variations in the loads that the structure will be subjected to.

Load factors for live and dead load are taken respectively as 2.2 and 1.5 in civil engineering. Let's understand why it is so.

Load Factor for Dead Load

Dead load is the weight of the structure itself, including all permanent fixtures and finishes. The weight of the structure is known with reasonable accuracy, and it is a constant value. However, there may be uncertainties in the weight of finishes and fixtures. Therefore, a load factor of 1.5 is used for dead load to account for these uncertainties.

Load Factor for Live Load

Live loads are the loads that are temporary and can change in magnitude and location. Examples of live loads include people, furniture, vehicles, and equipment. The magnitude and location of live loads are uncertain, and they can vary widely. Therefore, a load factor of 2.2 is used for live load to account for these uncertainties.

Conclusion

In conclusion, load factors are used in civil engineering to account for uncertainties and variations in the loads that the structure will be subjected to. Load factors for live and dead load are taken respectively as 2.2 and 1.5. A load factor of 1.5 is used for dead load to account for uncertainties in the weight of finishes and fixtures, whereas a load factor of 2.2 is used for live load to account for uncertainties in the magnitude and location of the load.
Free Test
Community Answer
The load factors for live and dead load are taken respectively as:a)1....
C
Explore Courses for Civil Engineering (CE) exam
Question Description
The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer?.
Solutions for The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer?, a detailed solution for The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The load factors for live and dead load are taken respectively as:a)1.5 and 2.2b)2.2 and 1.5c)1.5 and 1.5d)2.2 and 2.2Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev