A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:

  • a)
    10%

  • b)
    5%

  • c)
    8%

  • d)
    12%

Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A revised estimate is prepared when the expenditure on the work exceed...
The revised estimate is a detailed estimate for revised quantities and the rate of items of works originally provided in the estimate without material deviation of a structural nature from the design originally approved for a project.


It is required to be prepared for the following reasons:


i) When a sanctioned estimate is likely to exceed by more than 5% either from the rates being found insufficient or from cause whatsoever except important structural alteration.


ii) When the expenditure of works exceeds or is likely to exceed by more than 10% of the administrative approval (for work more than ₹5 lakhs/-)


iii) When there are material deviations from the original proposal but not due to the material deviation of structural nature.


iv) When it is found that the sanctioned estimate is more than the actual requirement.
View all questions of this test
Most Upvoted Answer
A revised estimate is prepared when the expenditure on the work exceed...
Revised Estimate in Civil Engineering

A revised estimate is a document prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction. In Civil Engineering, this document is important to ensure proper financial management and avoid any delays or legal issues.

Percentage Limit for Revised Estimate

The percentage limit for preparing a revised estimate is an important aspect to consider. It indicates the level of flexibility in the budget and the extent of deviation from the original plan. The correct answer for this question is option 'B', which means a revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than 10%.

Reasons for Preparing Revised Estimate

There are various reasons why a revised estimate may be necessary in Civil Engineering projects, such as:

1. Change in Scope of Work: The original plan may not be sufficient to cover all the requirements of the project, and additional work may be required. This can lead to an increase in the budget and the need for a revised estimate.

2. Increase in Material and Labor Costs: The price of materials and labor can fluctuate over time, and this can affect the budget of the project. If the costs increase significantly, a revised estimate may be necessary.

3. Unforeseen Circumstances: Sometimes, unexpected events can occur during the project that can impact the budget. For example, if there is damage to existing structures or utilities during excavation, additional work may be required, leading to a revised estimate.

4. Errors in Original Estimate: Sometimes, the original estimate may have errors or omissions that were not identified until the project was underway. In such cases, a revised estimate may be necessary to correct the budget.

Conclusion

In conclusion, a revised estimate is an important document in Civil Engineering that helps to manage the budget of a project. The percentage limit for preparing a revised estimate is 10%, and it is necessary when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction. There are various reasons why a revised estimate may be necessary, such as change in scope of work, increase in material and labor costs, unforeseen circumstances, and errors in original estimate.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer?
Question Description
A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer?.
Solutions for A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer?, a detailed solution for A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A revised estimate is prepared when the expenditure on the work exceeds or likely to exceed the amount of administrative sanction by more than:a)10%b)5%c)8%d)12%Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev