Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  A detailed estimate that is prepared when the... Start Learning for Free
A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:
  • a)
    Annual repair cost estimate
  • b)
    Revised cost estimate
  • c)
    Approximate quantity method cost estimate
  • d)
    Supplementary estimate
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
A detailed estimate that is prepared when there is a requirement of ad...
Supplementary estimate
(i) It is a detailed estimate of additional work and is prepared when additional works or changes are required to supplement the original works, during the execution of work.
(ii) Then a fresh detailed estimate of additional works is prepared in addition to the original works.
(iii) The abstract should show the amount of the original estimate and the total amount including the Supplementary amount, for which sanction is required.  
Revised estimate
It is a detailed estimate and is required to be prepared under any one of the following circumstances:
(i) When the original sanctioned estimate is likely to exceed by more than 5 %.
(ii) When the expenditure on work exceeds or likely to exceeds the amount of administrative sanctioned by more than 10 %.
(iii) If there is a change of rate or quantity of materials.
(iv) Major additions or alterations are introduced in the original work.
Free Test
Community Answer
A detailed estimate that is prepared when there is a requirement of ad...
Supplementary Estimate:

Definition:
A supplementary estimate is a detailed cost estimate that is prepared during the progress of the original work when there is a requirement for additional work beyond what was initially planned.

Purpose:
The main purpose of a supplementary estimate is to provide an accurate assessment of the additional costs that will be incurred due to the changes or additions to the original scope of work.

Preparation:
- The supplementary estimate is prepared by reviewing the new requirements, changes, or scope additions that have arisen during the course of the project.
- The estimate includes detailed calculations of the additional materials, labor, equipment, and other resources that will be needed to complete the extra work.

Approval:
Once the supplementary estimate is prepared, it is typically submitted to the client or project owner for approval before the additional work can proceed. This helps ensure transparency and agreement on the cost implications of the changes.

Documentation:
It is essential to document the supplementary estimate along with the original cost estimate and any other relevant project documents. This helps in maintaining a clear record of the project's financial status and changes throughout its lifecycle.
In conclusion, a supplementary estimate plays a crucial role in accurately assessing the additional costs associated with changes or additions to the original scope of work during a construction project. It helps project stakeholders make informed decisions and ensures transparency in project cost management.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer?
Question Description
A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer?.
Solutions for A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A detailed estimate that is prepared when there is a requirement of additional work during the progress of the original work is known as:a)Annual repair cost estimateb)Revised cost estimatec)Approximate quantity method cost estimated)Supplementary estimateCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev