Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  Most accurate method of estimation is based o... Start Learning for Free
Most accurate method of estimation is based on:
  • a)
    Building cost index estimate
  • b)
    Plinth area estimate
  • c)
    Detailed estimate
  • d)
    Cube rate estimate
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
Most accurate method of estimation is based on:a)Building cost index e...
Detailed estimate is the most accurate method and consist of working out the quantities of each of item of works and working the cost.
The dimensions are taken directly from the drawings and quantities of each item are calculated.
Finally abstracting and billing is done.
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer?
Question Description
Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Most accurate method of estimation is based on:a)Building cost index estimateb)Plinth area estimatec)Detailed estimated)Cube rate estimateCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev