In which type of estimate is 'Court yard' NOT considered?
  • a)
    Cube rate estimate
  • b)
    Plinth area estimate
  • c)
    Unit rate estimate
  • d)
    Lump sum estimate
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
In which type of estimate is Court yard NOT considered?a)Cube rate est...
In the field of civil engineering, various types of estimates are used to determine the cost of a construction project. These estimates help in planning and budgeting for the project. One such type of estimate is the plinth area estimate. In this type of estimate, the cost is calculated based on the plinth area of the building. However, the courtyard is not considered in this type of estimate.

Plinth area estimate:
The plinth area estimate is a widely used method for estimating the cost of a building. It involves calculating the cost based on the plinth area, which is the total built-up area of the building at the floor level. The plinth area includes all the covered areas of the building, such as rooms, corridors, and other enclosed spaces. It is an important parameter for estimating the cost of building materials, labor, and other resources required for the construction.

Why courtyard is not considered?
The courtyard is an open space within a building, usually enclosed by walls or surrounded by the building structure. It is typically used for outdoor activities, providing ventilation, and allowing natural light to enter the building. However, since the courtyard does not contribute to the built-up area of the building, it is not included in the plinth area estimate.

The courtyard is not considered in the plinth area estimate because it is an open space and does not require the same resources as the enclosed areas of the building. The construction cost of the courtyard is typically lower compared to the built-up areas as it does not involve walls, flooring, or roofing. Therefore, excluding the courtyard from the estimate helps in accurately calculating the cost of the actual building structure.

Conclusion:
In conclusion, the courtyard is not considered in the plinth area estimate. This estimate is based on the built-up area of the building, excluding the courtyard. By excluding the courtyard, the estimate accurately reflects the cost of the enclosed spaces in the building.
Free Test
Community Answer
In which type of estimate is Court yard NOT considered?a)Cube rate est...
Plinth area: 
  • It is the covered built-up area measured at the floor level of any storey or at the floor level of the basement.
  • The plinth area is also called a built-up area and is the entire area occupied by the building including internal and external walls.
  • It is generally 10-20% more than the carpet area.
In the Plinth area Estimate, Open areas, courtyard, and balconies should not be included in the plinth area valuation. This method is also known as an approximate estimate.
Cube rate estimate:
  • This type of estimate is done by multiplying the volume of the building by the unit cubic rate achieved from the previously (also recent) estimate.
  • This type of estimate is a little bit more accurate than the above-mentioned methods and mostly suitable for multi-storied buildings.
Unit rate estimate:
Uses predetermined output rates for labor and plant, in conjunction with a price per unit for materials, to calculate a rate per unit for some measured item of work, and this unit rate is then set against a total measured quantity.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer?
Question Description
In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In which type of estimate is Court yard NOT considered?a)Cube rate estimateb)Plinth area estimatec)Unit rate estimated)Lump sum estimateCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev