In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs?
Most Upvoted Answer
In plinth area method, the cost of construction is determined by multi...
**Plinth Area Method for Cost Estimation**

The plinth area method is a widely used technique in construction cost estimation. It determines the cost of construction by multiplying the outer length of the building, the plinth area rate, and the plinth area.

**Calculation of Plinth Area Estimate**

To calculate the plinth area estimate, we need to multiply the plinth area and the plinth area rate.

Given information:
- Plinth area = 400 square feet
- Plinth area rate = Rs. 540 per square feet

**Plinth Area Estimate Formula:**
Plinth Area Estimate = Plinth Area x Plinth Area Rate

Plinth Area Estimate = 400 square feet x Rs. 540 per square feet

Plinth Area Estimate = Rs. 216,000

Therefore, the plinth area estimate of the construction is Rs. 216,000.

**Answer: A) Outer breadth of the building, 2.16 lakhs**

The correct option is A) Outer breadth of the building, 2.16 lakhs, which matches the calculated plinth area estimate.

Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs?
Question Description
In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs?.
Solutions for In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs? defined & explained in the simplest way possible. Besides giving the explanation of In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs?, a detailed solution for In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs? has been provided alongside types of In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs? theory, EduRev gives you an ample number of questions to practice In plinth area method, the cost of construction is determined by multiplying outer length of the building, plinth area rate and . If the plinth area and plinth area rate of a construction are 400 square feet and Rs. 540 per square feet respectively, then plinth area estimate of the construction is A Outer breadth of the building, 2.16 lakhs B Inner breadth of the building, 2.16 lakhs C Outer breadth of the building, 1.35 lakhs D Inner breadth of the building, 1.35 lakhs? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev