The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?
Add 15 % of the estimate as additional charges for public health and electric services also.
  • a)
    945000
  • b)
    724500
  • c)
    6300000
  • d)
    7245000
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
The rough cost estimate for a building having Plinth area and Plinth a...
Rough estimate of a building based on plinth area will be:
C1 = Plinth area x Plinth area rate
C1 = 700 x 9000 = 6300000 Rs.
Additional 15 % charges for public health and electric services,
C2 = 0.15 x 6300000 = 945000 Rs
Total rough estimate of the building = C+ C2
= 6300000 + 945000 = 7245000.
View all questions of this test
Most Upvoted Answer
The rough cost estimate for a building having Plinth area and Plinth a...
Given:
Plinth area = 700 sq. m
Plinth area rate = Rs. 9000/sq. m

To find:
Rough cost estimate

Solution:

Rough cost estimate = Plinth area x Plinth area rate

= 700 x 9000

= Rs. 6,300,000

Additional charges for public health and electric services = 15% of the rough cost estimate

= 15/100 x 6,300,000

= Rs. 945,000

Total cost estimate = Rough cost estimate + Additional charges

= 6,300,000 + 945,000

= Rs. 7,245,000

Therefore, the correct option is (D) 7245000.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer?
Question Description
The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer?.
Solutions for The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer?, a detailed solution for The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The rough cost estimate for a building having Plinth area and Plinth area rate as 700 square meter and 9000 Rs respectively is?Add 15 % of the estimate as additional charges for public health and electric services also.a)945000b)724500c)6300000d)7245000Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev