Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  What is the estimate (Rs.) for a building wit... Start Learning for Free
What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)
  • a)
    150000
  • b)
    450080
  • c)
    2423000
  • d)
    9272000
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
What is the estimate (Rs.) for a building with a plinth area of 2000 s...
Plinth area = 2000 m2
Rate per m2 = Rs. 3800
Total cost of plinth area = 3800 × 2000 = Rs. 7600000
15% Electric installation = Rs. 1140000
7% Miscellaneous = Rs. 532000
Final cost of the building = Rs. 7600000 + Rs. 1140000 + Rs. 532000
= Rs. 9272000
View all questions of this test
Most Upvoted Answer
What is the estimate (Rs.) for a building with a plinth area of 2000 s...
Estimating the Cost of a Building

Given:
Plinth area of the building = 2000 sq. m
Rate per sq. m = Rs. 3800
Additional costs:
- Electric installation = 15% of the total cost
- Miscellaneous = 7% of the total cost

To estimate the cost of the building, we can follow these steps:

Step 1: Calculate the total cost of the building
Total cost = Plinth area × Rate per sq. m
Total cost = 2000 sq. m × Rs. 3800/sq. m
Total cost = Rs. 7,600,000

Step 2: Calculate the additional costs
Electric installation cost = 15% of the total cost
Electric installation cost = 0.15 × Rs. 7,600,000
Electric installation cost = Rs. 1,140,000

Miscellaneous cost = 7% of the total cost
Miscellaneous cost = 0.07 × Rs. 7,600,000
Miscellaneous cost = Rs. 532,000

Step 3: Calculate the final estimate
Final estimate = Total cost + Electric installation cost + Miscellaneous cost
Final estimate = Rs. 7,600,000 + Rs. 1,140,000 + Rs. 532,000
Final estimate = Rs. 9,272,000

Therefore, the estimate for the building with a plinth area of 2000 sq. m and a rate of Rs. 3800 per sq. m, considering the additional costs, is Rs. 9,272,000 (option D).
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer?
Question Description
What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer?.
Solutions for What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer?, a detailed solution for What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice What is the estimate (Rs.) for a building with a plinth area of 2000 sq. m with rate of Rs. 3800 per sq. m? (Consider the adds of 15% of electric installation and 7% of miscellaneous)a)150000b)450080c)2423000d)9272000Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev