MTM is a work measurement technique by: 
  • a)
    Stopwatch study    
  • b)
    Work sampling study  
  • c)
    Pre-determined motion time systems  
  • d)
    Past data comparison 
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
MTM is a work measurement technique by:a)Stopwatch study b)Work sampl...
MTM (Methods-time measurement) is based on use of standard time for work elements that have been predetermined from long periods of observation and analysis.
View all questions of this test
Most Upvoted Answer
MTM is a work measurement technique by:a)Stopwatch study b)Work sampl...
MTM is a work measurement technique by Pre-determined motion time systems

Pre-determined motion time systems (PMTS) is a work measurement technique that is used to determine the time required to perform a specific task or operation. It is based on the principle that the time required to perform a task can be broken down into a series of basic motion elements, each with a predetermined time value.

What is MTM?

MTM stands for Methods-Time Measurement, which is a predetermined motion time system that is widely used in industries to establish standard times for performing various tasks. It is a systematic and scientific approach to measure the time required to perform a specific task, taking into account various factors such as the method, motion, and human capabilities.

How does MTM work?

MTM uses a set of predetermined time values called motion units to measure the time required for various basic motions involved in a task. These motion units are based on extensive studies and observations of human motions and have been standardized for different types of motions such as reach, grasp, move, and release.

Advantages of MTM:
- MTM provides a standardized and objective method for measuring the time required to perform a task, which helps in establishing fair and accurate time standards.
- It allows for the comparison of different methods and techniques used for performing a task, helping in identifying the most efficient and productive method.
- MTM helps in identifying and eliminating unnecessary or inefficient motions, leading to improved productivity and reduced fatigue.
- It provides a basis for determining labor costs and estimating production rates accurately.
- MTM can be used for job design and work simplification, enabling the development of more efficient and ergonomic workstations.

Conclusion

MTM is a valuable work measurement technique that allows for the accurate determination of time required to perform a task. It is based on the use of predetermined motion time systems, such as the MTM system, which provides standardized time values for different basic motions. By using MTM, organizations can establish fair and accurate time standards, identify and eliminate inefficiencies, and improve overall productivity and worker well-being.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer?
Question Description
MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer?.
Solutions for MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice MTM is a work measurement technique by:a)Stopwatch study b)Work sampling study c)Pre-determined motion time systems d)Past data comparisonCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev