The phases of highway planning do not include the followinga)Assessmen...
Financing of the highway is done after the planning of highway after getting approval from the government, before the assessment, preparation and DPR are prepared.
View all questions of this test
The phases of highway planning do not include the followinga)Assessmen...
Highway Planning Phases
Assessment of Road Length Requirement
This phase involves determining the length of the road that is required to connect the origin and the destination of the highway. The road length requirement is based on several factors, including the population density, the distance between the origin and destination, and the type of transportation service required.
Preparation of Master Plan
The preparation of a master plan involves creating a blueprint for the highway project, which includes the alignment, cross-section, and other design elements. The master plan also includes the construction and maintenance costs, as well as the proposed timeline for the project.
Showing the Phasing of a Plan in Five-Year Plan
The phasing of a plan in a five-year plan involves breaking down the project into smaller, manageable phases that can be completed within a five-year period. This helps to ensure that the project is completed on time and within budget.
Financing
Financing involves determining the funding sources and securing the necessary funds to complete the project. This includes identifying potential investors, applying for grants or loans, and developing a financial plan that outlines the project's costs and revenue streams.
Correct Answer: D - Financing
The phases of highway planning do not include financing since it is a separate process that involves securing the necessary funds to complete the project. While financing is an important aspect of highway planning, it is not considered one of the primary phases of the planning process.