A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is - 
  • a)
    Rs. 8628
  • b)
    Rs. 6280
  • c)
    Rs. 2680
  • d)
    Rs. 1000
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A ring type of foundation is constructed with internal and external di...
Total volume of RCC slab is,V=
Totalcost=V×1000=
View all questions of this test
Most Upvoted Answer
A ring type of foundation is constructed with internal and external di...
Given Data:

Internal diameter of the ring foundation (D1) = 8m

External diameter of the ring foundation (D2) = 12m

Thickness of the slab (t) = 10 cm = 0.1 m

Cost of RCC per cubic meter = Rs. 1000

To find:

The cost of RCC used in the slab

Solution:

1. Calculation of Volume of RCC slab

The volume of RCC slab can be calculated by subtracting the volume of the inner circle from the volume of the outer circle.

Volume of the outer circle = π/4 x D2² x t

Volume of the inner circle = π/4 x D1² x t

Volume of the RCC slab = π/4 x (D2² - D1²) x t

= π/4 x ((12)² - (8)²) x 0.1

= 1.6 m³

2. Calculation of Cost of RCC used in the slab

Cost of 1 m³ of RCC = Rs. 1000

Cost of 1.6 m³ of RCC = 1000 x 1.6 = Rs. 1600

Therefore, the cost of RCC used in the slab is Rs. 1600.

Answer:

Option (b) Rs. 6280
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer?
Question Description
A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer?.
Solutions for A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer?, a detailed solution for A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A ring type of foundation is constructed with internal and external diameters of 8 m and 12 m respectively. If thickness of the slab is 10 cm and cost of RCC per cubic meter is Rs. 1000, the cost of RCC used in the slab is -a)Rs. 8628b)Rs. 6280c)Rs. 2680d)Rs. 1000Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev