Electrical Engineering (EE) Exam  >  Electrical Engineering (EE) Questions  >  Power plant having maximum demand more than i... Start Learning for Free
Power plant having maximum demand more than installed capacity will have utilization factor:
  • a)
    Less than 100%
  • b)
    Equal to 100%
  • c)
    More than 100%
  • d)
    None of these
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
Power plant having maximum demand more than installed capacity will ha...
If maximum demand is more than installed capacity, station output will be more than the installed plant capacity.
Hence utilization factor will be more than 100%
View all questions of this test
Most Upvoted Answer
Power plant having maximum demand more than installed capacity will ha...
Utilization Factor of a Power Plant

The utilization factor of a power plant is a measure of how efficiently the plant is being used relative to its installed capacity. It is calculated by dividing the actual power output of the plant by its maximum possible output if it were running at full capacity.

Maximum Demand and Installed Capacity

The maximum demand refers to the peak power requirement at a specific time, which represents the highest level of electricity consumption within a given period. On the other hand, the installed capacity of a power plant is the maximum amount of power that it can generate under ideal conditions.

Understanding the Utilization Factor in Relation to Maximum Demand and Installed Capacity

When the maximum demand is less than the installed capacity of a power plant, the utilization factor will be less than 100%. This is because the plant is not operating at its full capacity and is not being fully utilized. In this scenario, the actual power output is lower than the maximum possible output.

However, when the maximum demand exceeds the installed capacity of a power plant, the utilization factor will be greater than 100%. This means that the plant is being overloaded and is operating beyond its designed capacity. In such a situation, the actual power output exceeds the maximum possible output, leading to a utilization factor higher than 100%.

Significance of a Utilization Factor Greater than 100%

A utilization factor greater than 100% indicates that the power plant is being pushed beyond its limits to meet the high demand for electricity. While this may seem beneficial in the short term as it allows the plant to generate more power than its installed capacity, it is not sustainable in the long run. Operating a power plant above its rated capacity for extended periods can lead to various issues, including:

1. Increased wear and tear: The equipment and components of the power plant may experience accelerated deterioration due to the higher stress levels.

2. Reduced efficiency: Operating beyond the rated capacity can negatively impact the overall efficiency of the plant, leading to higher fuel consumption and lower energy conversion efficiency.

3. Safety risks: Overloading a power plant can pose safety hazards as it may exceed the design limits of certain equipment, potentially leading to failures or accidents.

4. Increased maintenance and repair costs: The higher operating stress levels can result in more frequent breakdowns and maintenance requirements, leading to increased operational costs.

Therefore, while a utilization factor greater than 100% may be possible in certain situations, it is not desirable or sustainable in the long term. Power plants are typically designed to operate within their rated capacity to ensure optimal performance, efficiency, and longevity.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer?
Question Description
Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer? for Electrical Engineering (EE) 2024 is part of Electrical Engineering (EE) preparation. The Question and answers have been prepared according to the Electrical Engineering (EE) exam syllabus. Information about Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for Electrical Engineering (EE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer?.
Solutions for Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Electrical Engineering (EE). Download more important topics, notes, lectures and mock test series for Electrical Engineering (EE) Exam by signing up for free.
Here you can find the meaning of Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Power plant having maximum demand more than installed capacity will have utilization factor:a)Less than 100%b)Equal to 100%c)More than 100%d)None of theseCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice Electrical Engineering (EE) tests.
Explore Courses for Electrical Engineering (EE) exam

Top Courses for Electrical Engineering (EE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev