Civil Engineering (CE) Exam  >  Civil Engineering (CE) Questions  >  An automobile plant contracted to buy shock a... Start Learning for Free
An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.
The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y is
  • a)
    0.288
  • b)
    0.334
  • c)
    0.667
  • d)
    0.720
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
An automobile plant contracted to buy shock absorbers from two supplie...
View all questions of this test
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer?
Question Description
An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer?.
Solutions for An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer?, a detailed solution for An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice An automobile plant contracted to buy shock absorbers from two suppliers X and Y. X supplies 60% and Y supplies 40% of the shock absorbers. All shock absorbers are subjected to a quality test. The ones that pass the quality test are considered reliable. Of X’s shock absorbers, 96% are reliable. Of Y’s shock absorbers, 72% are reliable.The probability that a randomly chosen shock absorber, which is found to be reliable, is made by Y isa)0.288b)0.334c)0.667d)0.720Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses