Quant Exam  >  Quant Questions  >  A typing work is done by three person P, Q an... Start Learning for Free
A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?
  • a)
    30hrs
  • b)
    40hrs
  • c)
    25hrs
  • d)
    45hrs
  • e)
    50hrs
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A typing work is done by three person P, Q and R. P alone takes 10 hou...
View all questions of this test
Most Upvoted Answer
A typing work is done by three person P, Q and R. P alone takes 10 hou...
Given Information:

Three people, P, Q, and R, are involved in a typing work.
P takes 10 hours to type a single booklet.
Q and R together take 4 hours to complete a booklet.

Approach:

Let's assume that the total work to type a booklet is represented by "x".

We can find the individual work rates of P, Q, and R by using the concept of work done in unit time.

Calculations:

Let's assume the work done by P in 1 hour is "P's work rate".
Therefore, P's work rate = x/10

Similarly, let's assume the work done by Q in 1 hour is "Q's work rate" and the work done by R in 1 hour is "R's work rate".
Therefore, (Q's work rate) + (R's work rate) = x/4

Given that P, Q, and R together completed 14 booklets, we can equate the total work done by them with the work done by each person individually.

Total work done by P, Q, and R = (P's work rate + Q's work rate + R's work rate) × time taken

We need to find the total time taken by P, Q, and R together to complete the work.

Substituting the values, we have:
14x = [(x/10) + (x/4)] × time taken

Simplifying the equation, we get:
14 = (1/10 + 1/4) × time taken

Solving further:
14 = (2/20 + 5/20) × time taken
14 = (7/20) × time taken

Multiplying both sides by 20/7, we get:
time taken = 40 hours (option B)

Answer:

The three people worked together for 40 hours to complete the 14 booklets.
Explore Courses for Quant exam

Similar Quant Doubts

A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer?
Question Description
A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer? for Quant 2024 is part of Quant preparation. The Question and answers have been prepared according to the Quant exam syllabus. Information about A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Quant 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Quant. Download more important topics, notes, lectures and mock test series for Quant Exam by signing up for free.
Here you can find the meaning of A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A typing work is done by three person P, Q and R. P alone takes 10 hours to type a single booklet but B and C working together takes 4 hours, for the completion of the same booklet. If all of them worked together and completed 14 booklets, then how many hours have they worked?a)30hrsb)40hrsc)25hrsd)45hrse)50hrsCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Quant tests.
Explore Courses for Quant exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev