Consider the following activities:
1. Pouring of concrete
2. Erection of formwork
3. Curing of concrete
4. Removal of formwork
What is the correct sequence on a network of these activities?
  • a)
    1-2-3-4
  • b)
    2-1-4-3
  • c)
    2-1-3-4
  • d)
    1-3-2-4
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Consider the following activities:1. Pouring of concrete2. Erection of...
Correct sequence of activities is:
a) Erection of formwork
b) Placing of reinforcement
c) Pouring of concrete
d) Compaction of concrete
e) Removal of formwork
f) Curing
View all questions of this test
Most Upvoted Answer
Consider the following activities:1. Pouring of concrete2. Erection of...
Pouring of Concrete
The first activity in the sequence is pouring of concrete. This involves the process of placing the concrete mix into the desired area or formwork. It is important to ensure that the concrete is poured evenly and at the right consistency to achieve the desired strength and durability.

Erection of Formwork
The second activity is the erection of formwork. Formwork refers to the temporary structure or mold that holds the concrete in place during the pouring process. It provides the shape and support needed for the concrete to set and harden. The formwork can be made of various materials such as wood, steel, or plastic.

Curing of Concrete
The third activity is the curing of concrete. Curing is a critical process that allows the concrete to gain strength and durability over time. It involves providing the right conditions (e.g., temperature, moisture) for the hydration process to occur. Curing helps prevent cracking, shrinkage, and other defects in the concrete.

Removal of Formwork
The final activity in the sequence is the removal of formwork. Once the concrete has sufficiently cured and gained enough strength to support itself, the formwork can be removed. This is usually done carefully to avoid any damage to the concrete. The timing for formwork removal depends on factors such as the type of concrete, ambient conditions, and desired finish.

Correct Sequence
Based on the given activities, the correct sequence on a network would be 2-1-4-3.
- The formwork needs to be erected first to provide the necessary structure for pouring the concrete.
- Once the formwork is in place, the concrete can be poured into it.
- After the concrete is poured, it needs to cure for a certain period of time to gain strength and durability.
- Finally, the formwork can be removed once the concrete has sufficiently cured.

Explanation
The correct sequence is 2-1-4-3 because the formwork needs to be in place before the concrete can be poured. Similarly, the concrete needs to cure before the formwork can be safely removed. Therefore, the activities should follow this sequence to ensure a successful and efficient construction process.
Free Test
Community Answer
Consider the following activities:1. Pouring of concrete2. Erection of...
C
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer?
Question Description
Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer?.
Solutions for Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following activities:1. Pouring of concrete2. Erection of formwork3. Curing of concrete4. Removal of formworkWhat is the correct sequence on a network of these activities?a)1-2-3-4b)2-1-4-3c)2-1-3-4d)1-3-2-4Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev