Question Description
Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer? for Computer Science Engineering (CSE) 2024 is part of Computer Science Engineering (CSE) preparation. The Question and answers have been prepared
according to
the Computer Science Engineering (CSE) exam syllabus. Information about Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Computer Science Engineering (CSE) 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer?.
Solutions for Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Computer Science Engineering (CSE).
Download more important topics, notes, lectures and mock test series for Computer Science Engineering (CSE) Exam by signing up for free.
Here you can find the meaning of Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice Two concurrent processes P1 and P2 use four shared resources R1, R2, R3 and R4, as shown below.Both processes are started at the same time, and each resource can be accessed by only one process at a time The following scheduling constraints exist between the access of resources by the processes: P2 must complete use of R1 before P1 gets access to R1 P1 must complete use of R2 before P2 gets access to R2. P2 must complete use of R3 before P1 gets access to R3. P1 must complete use of R4 before P2 gets access to R4.There are no other scheduling constraints between the processes. If only binary semaphores are used to enforce the above scheduling constraints, what is the minimum number of binary semaphores needed?a)1b)2c)3d)4Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Computer Science Engineering (CSE) tests.