Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?
  • a)
    2 days
  • b)
    3 days
  • c)
    4 days
  • d)
    6 days
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Amar started doing work, but left it after 6 days. Chetan completed th...
1 day's work of Chetan = 1/24
8 days' work of Chetan = 8 × 1/24 = 1/3
Hence, the remaining work that Chetan completed in 8 days = 1/3
⇒ Work done by Amar in 6 days = 1 – 1/3 = 2/3
⇒ 6 days' work of Amar = 2/3
⇒ 1 day's work of Amar = 1/6 × 2/3 = 1/9
This means that Amar would have done the whole work in 9 days.
∴ Amar would have taken (9 – 6 = 3) days to complete the remaining work.
View all questions of this test
Most Upvoted Answer
Amar started doing work, but left it after 6 days. Chetan completed th...
Chetan efficiency = 1/24
work done by him in 8 days =1/24*8
i.e 1/3
remaining work = 1-1/3 = 2/3
2/3 work is done by Amar in 6 days
He can complete the whole world in =(6*3)/2
i.e 9 days
Then, remaining work of (1/3) can be done by him in 9/3 days
i.e 3days
Free Test
Community Answer
Amar started doing work, but left it after 6 days. Chetan completed th...
Calculation:
- Let's assume the total work is represented by 24 units.
- Amar completed work in 6 days, so he completed 6 units of work each day.
- Therefore, Amar completed 6 * 6 = 36 units of work in 6 days.
- Chetan completed the remaining work which is 24 - 36 = 8 units in 8 days.
- Chetan's work rate is 1 unit per day (24 days to complete 24 units), so in 8 days, he completed 8 units.

Calculating Amar's work rate:
- Amar completed 36 units in 6 days, so his work rate is 36 / 6 = 6 units per day.
- Chetan's work rate is 1 unit per day.
- Combined work rate of Amar and Chetan is 6 + 1 = 7 units per day.

Finding the remaining work for Amar:
- Since Chetan completed 8 units of work in 8 days, he would have taken 24 days to complete the remaining 16 units of work alone.
- Now, Amar has to complete these remaining 16 units of work.

Calculating the time taken by Amar to complete the remaining work:
- Amar's work rate is 6 units per day, and the remaining work is 16 units.
- Therefore, Amar will take 16 / 6 = 2.67 days to complete the remaining work.
Therefore, the number of days Amar would take to complete the remaining work is approximately 3 days. So, the correct answer is option B.
Explore Courses for Railways exam
Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer?
Question Description
Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer? for Railways 2024 is part of Railways preparation. The Question and answers have been prepared according to the Railways exam syllabus. Information about Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Railways 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Railways. Download more important topics, notes, lectures and mock test series for Railways Exam by signing up for free.
Here you can find the meaning of Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Amar started doing work, but left it after 6 days. Chetan completed the remaining work in 8 days. If Chetan alone can do the work in 24 days, how many days would Amar take to complete the remaining work?a)2 daysb)3 daysc)4 daysd)6 daysCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Railways tests.
Explore Courses for Railways exam

Top Courses for Railways

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev