The settlement ratio of pile group is generally
  • a)
    less than 0.25
  • b)
    between 0.5 and 0.75
  • c)
    between 0.75 and 1.00
  • d)
    more than 1.00
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
The settlement ratio of pile group is generallya)less than 0.25b)betwe...
The settlement of a group of piles in mnore than the settlement of a single pile even when the load on the single pile and the load on each pile of the pile group are same. This is because of the fact that the zone of influence of a pile group is much deeper than that of a single pile.
View all questions of this test
Most Upvoted Answer
The settlement ratio of pile group is generallya)less than 0.25b)betwe...
Settlement Ratio of Pile Group

The settlement ratio of pile group is the ratio of the settlement of the pile group to the settlement of a single pile. It is denoted by Sgp/Sp, where Sgp is the settlement of the pile group and Sp is the settlement of a single pile.

The settlement ratio of pile group depends on various factors such as the number of piles, their spacing, diameter, length, soil properties, and loading conditions. Generally, the settlement ratio of pile group is more than 1.00, which means that the settlement of pile group is more than the settlement of a single pile.

Factors affecting Settlement Ratio of Pile Group

1. Number of Piles: The settlement ratio of pile group increases with the increase in the number of piles. This is because the pile group distributes the load over a larger area, resulting in less settlement of individual piles.

2. Spacing of Piles: The settlement ratio of pile group increases with the increase in the spacing of piles. This is because the spacing of piles affects the interaction between adjacent piles and the soil, and a larger spacing reduces the interaction.

3. Diameter of Piles: The settlement ratio of pile group decreases with the increase in the diameter of piles. This is because the larger diameter piles have more resistance to deformation and can support more load, resulting in less settlement.

4. Length of Piles: The settlement ratio of pile group decreases with the increase in the length of piles. This is because the longer piles penetrate deeper into the soil and have more resistance to deformation, resulting in less settlement.

5. Soil Properties: The settlement ratio of pile group depends on the soil properties such as stiffness, strength, and compressibility. The softer and more compressible the soil, the higher the settlement ratio.

6. Loading Conditions: The settlement ratio of pile group depends on the loading conditions such as the magnitude and distribution of load. The larger the load and the more concentrated it is, the higher the settlement ratio.

Conclusion

In summary, the settlement ratio of pile group is generally more than 1.00, which means that the settlement of pile group is more than the settlement of a single pile. The settlement ratio depends on various factors such as the number of piles, their spacing, diameter, length, soil properties, and loading conditions.
Explore Courses for Civil Engineering (CE) exam
Question Description
The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer?.
Solutions for The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer?, a detailed solution for The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The settlement ratio of pile group is generallya)less than 0.25b)between 0.5 and 0.75c)between 0.75 and 1.00d)more than 1.00Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev