Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.
The critical path (CP) in the network is
  • a)
    1-2-3-5
  • b)
    1-4-3-5
  • c)
    1-2-3-4-5
  • d)
    1-4-5
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Following data refers to the activities of a project, where, node 1 re...
The critical path is the sequence of activities with the longest duration. A delay in any of these activities will result in a delay for the whole project.
Critical path = 1‒4‒3‒5 = 3+3+2 = 8
Note: Critical path is the longest path through a network of activities, which in-turn, determines the shortest time possible to complete all tasks in the network (i.e. the shortest time to complete the project).
View all questions of this test
Most Upvoted Answer
Following data refers to the activities of a project, where, node 1 re...
The critical path is the sequence of activities with the longest duration. A delay in any of these activities will result in a delay for the whole project.
Critical path = 1‒4‒3‒5 = 3+3+2 = 8
Note: Critical path is the longest path through a network of activities, which in-turn, determines the shortest time possible to complete all tasks in the network (i.e. the shortest time to complete the project).
Free Test
Community Answer
Following data refers to the activities of a project, where, node 1 re...
Explore Courses for GATE exam
Question Description
Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? for GATE 2025 is part of GATE preparation. The Question and answers have been prepared according to the GATE exam syllabus. Information about Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for GATE 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer?.
Solutions for Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE. Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice GATE tests.
Explore Courses for GATE exam
Signup to solve all Doubts
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev