Question Description
Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? for GATE 2025 is part of GATE preparation. The Question and answers have been prepared
according to
the GATE exam syllabus. Information about Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for GATE 2025 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer?.
Solutions for Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for GATE.
Download more important topics, notes, lectures and mock test series for GATE Exam by signing up for free.
Here you can find the meaning of Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer?, a detailed solution for Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice Following data refers to the activities of a project, where, node 1 refers to the start and node 5 refers to the end of the project.The critical path (CP) in the network isa)1-2-3-5b)1-4-3-5c)1-2-3-4-5d)1-4-5Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice GATE tests.