The standard project flood is
  • a)
    smaller than the probable maximum flood
  • b)
    the same as the probable maximum flood
  • c)
    the same as the design flood
  • d)
    larger than the probable maximum flood by a factor implying safety factor
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
The standard project flood isa)smaller than the probable maximum flood...
The flood that would result from a sever combination of meteorological and hydrological factors that are reasonably applicable to the region. Extremely rare combinations of factors are excluded.
View all questions of this test
Most Upvoted Answer
The standard project flood isa)smaller than the probable maximum flood...
Standard Project Flood vs Probable Maximum Flood

In the field of hydraulics and hydrology, the design of water management structures like dams, reservoirs, and flood control systems requires the estimation of flood magnitudes that may occur in a given region. Two important terms used in this context are the standard project flood and the probable maximum flood.

Standard Project Flood

The standard project flood (SPF) is an estimate of the largest flood that can be expected to occur at a given location under normal or average conditions. It is calculated based on statistical analysis of historical flood data, rainfall patterns, and other relevant factors. The SPF is typically used as a basis for designing or evaluating flood control structures, such as levees, spillways, and water retention basins.

Probable Maximum Flood

The probable maximum flood (PMF) is an estimate of the largest flood that could theoretically occur at a given location under the most extreme meteorological and hydrological conditions that are reasonably possible. The PMF is not based on historical data, but rather on hypothetical scenarios that assume the most severe storm events and watershed conditions that could realistically occur. The PMF is used as a safety factor in the design of water management structures to ensure that they can withstand the most severe flooding events.

Comparison of SPF and PMF

The SPF is generally smaller than the PMF because it is based on historical data and average or normal conditions, whereas the PMF is based on extreme scenarios that may not have occurred in the past. The PMF is typically used as a safety factor in the design of water management structures, with the assumption that the actual flood magnitudes will not exceed this value. However, there is always some uncertainty in flood forecasting, and unexpected events can occur that exceed even the PMF. Therefore, it is important to design water management structures with some margin of safety beyond the PMF, to ensure their resilience against extreme events.
Explore Courses for Civil Engineering (CE) exam
Question Description
The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer?.
Solutions for The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The standard project flood isa)smaller than the probable maximum floodb)the same as the probable maximum floodc)the same as the design floodd)larger than the probable maximum flood by a factor implying safety factorCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.