The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler is
  • a)
    piston sampler, chunk sampler, split spoon sampler, remoulded sampler
  • b)
    chunk sampler, piston sampler, split spoon sampler, remoulded sampler
  • c)
    piston sampler, chunk sampler, remoulded sampler, split spoon sampler
  • d)
    chunk sampler, piston sampler, remoulded sampler, split spoon sampler
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
The correct sequence of the increasing order of the disturbance to soi...
Piston sampler causes minimum disturbance and remoulded sampler tends to disturb the soil structure completely.
View all questions of this test
Most Upvoted Answer
The correct sequence of the increasing order of the disturbance to soi...
Sequence of Disturbance to Soil Samples

The disturbance to soil samples obtained from different types of samplers can vary depending on the type of sampler used. The correct sequence of increasing order of disturbance to soil samples obtained from chunk, piston, split spoon, and remoulded sampler is as follows:

1. Piston Sampler
The piston sampler is designed to collect undisturbed soil samples. It uses a metal tube that is pushed into the soil to collect a cylindrical soil sample. The disturbance to the soil sample obtained from a piston sampler is the least as the sample is collected without any disturbance.

2. Chunk Sampler
The chunk sampler is used to collect disturbed soil samples. It uses a metal tube with a cutting edge that is driven into the soil to collect a sample. The sample obtained from a chunk sampler is more disturbed compared to the sample obtained from a piston sampler.

3. Split Spoon Sampler
The split spoon sampler is used to collect disturbed soil samples. It consists of a metal tube with a split at the bottom and a cutting edge at the top. The sampler is driven into the soil, and the sample is collected by splitting the tube. The sample obtained from a split spoon sampler is more disturbed compared to the sample obtained from a chunk sampler.

4. Remoulded Sampler
The remoulded sampler is used to collect highly disturbed soil samples. It is designed to simulate the process of soil compaction in the laboratory. The soil sample obtained from a remoulded sampler is the most disturbed compared to the samples obtained from all other samplers.

Therefore, the correct sequence of increasing order of disturbance to soil samples obtained from chunk, piston, split spoon, and remoulded sampler is piston sampler, chunk sampler, split spoon sampler, and remoulded sampler.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer?
Question Description
The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer?.
Solutions for The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The correct sequence of the increasing order of the disturbance to soil samples obtained from chunk, piston, split spoon and remoulded sampler isa)piston sampler, chunk sampler, split spoon sampler, remoulded samplerb)chunk sampler, piston sampler, split spoon sampler, remoulded samplerc)piston sampler, chunk sampler, remoulded sampler, split spoon samplerd)chunk sampler, piston sampler, remoulded sampler, split spoon samplerCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam