In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days is
  • a)
    4
  • b)
    8
  • c)
    10
  • d)
    12
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
In a PERT network the expected time to finish one activity is 22 days ...
View all questions of this test
Most Upvoted Answer
In a PERT network the expected time to finish one activity is 22 days ...
PERT Network
- PERT (Program Evaluation and Review Technique) is a project management technique used to analyze and represent the tasks involved in completing a project.
- It is a network-based scheduling method that considers both the time and resources required to complete each activity in a project.

Expected Time and Variance
- In a PERT network, each activity is assigned an expected time (te) and a variance (σ^2).
- The expected time represents the most likely time required to complete the activity.
- The variance provides a measure of the uncertainty or variability associated with the expected time.

Ratio of Pessimistic Time to Optimistic Time
- In PERT, the expected time (te) is calculated as a weighted average of the optimistic time (to), most likely time (tm), and pessimistic time (tp) for each activity.
- The formula to calculate expected time is: te = (to + 4tm + tp) / 6
- Given that the expected time for the activity is 22 days, we can substitute this value into the formula and solve for the ratio of pessimistic time (tp) to optimistic time (to).

Calculation
- te = (to + 4tm + tp) / 6
- 22 = (to + 4(23) + tp) / 6
- 132 = to + 92 + tp
- to + tp = 132 - 92
- to + tp = 40

- We are given that the variance (σ^2) of the activity is 16 days.
- The variance is calculated using the formula: σ^2 = ((tp - to) / 6)^2
- Substituting the given values into the formula, we can solve for tp/to.

Calculation
- 16 = ((tp - to) / 6)^2
- 4 = (tp - to) / 6
- 24 = tp - to
- tp = 24 + to

- Now we can substitute the value of tp into the equation to + tp = 40.

Calculation
- to + (24 + to) = 40
- 2to = 40 - 24
- 2to = 16
- to = 8

- Finally, the ratio of pessimistic time to optimistic time is tp/to = (24 + to) / to = (24 + 8) / 8 = 32 / 8 = 4.

Answer
- Therefore, the correct answer is option A) 4.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer?
Question Description
In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer?.
Solutions for In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer?, a detailed solution for In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In a PERT network the expected time to finish one activity is 22 days and variance of the activity is 16 days. The ratio of pessimistic time to optimistic time if most likely time for finishing the activity is 23 days isa)4b)8c)10d)12Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev