A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?
  • a)
    5.0 days
  • b)
    7.5 days
  • c)
    8.0 days
  • d)
    8.5 days
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
A PERT activity has an optimistic time estimate of 3 days, pessimisti...
View all questions of this test
Most Upvoted Answer
A PERT activity has an optimistic time estimate of 3 days, pessimisti...
Question Analysis:
We are given the optimistic, pessimistic, and most likely time estimates for a PERT activity. PERT (Program Evaluation and Review Technique) is a statistical tool used in project management to analyze and represent the tasks involved in completing a project. The expected time of an activity can be calculated using the formula: expected time = (optimistic time + 4 * most likely time + pessimistic time) / 6.

Calculation:
Given: Optimistic time (to) = 3 days, Most likely time (tm) = 10 days, Pessimistic time (tp) = 8 days.

Using the formula: expected time = (to + 4 * tm + tp) / 6

Substituting the given values: expected time = (3 + 4 * 10 + 8) / 6

Simplifying the expression: expected time = (3 + 40 + 8) / 6

Further simplifying: expected time = 51 / 6

Dividing: expected time = 8.5 days

Therefore, the expected time for this activity is 8.5 days.

Answer:
The correct answer is option D) 8.5 days.
Free Test
Community Answer
A PERT activity has an optimistic time estimate of 3 days, pessimisti...
Question error pessimistic time is maximum possible time
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer?
Question Description
A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer?.
Solutions for A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A PERT activity has an optimistic time estimate of 3 days, pessimistic time estimate of 8 days, and a most likely time estimate of 10 days. What is the expected time of this activity?a) 5.0 daysb) 7.5 daysc) 8.0 daysd) 8.5 daysCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev