In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?
  • a)
    1 minute
  • b)
    5 minutes
  • c)
    8 minutes
  • d)
    18 minutes
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
In a small engineering project, for an activity, the optimistic time...
Expected time
View all questions of this test
Most Upvoted Answer
In a small engineering project, for an activity, the optimistic time...


Expected Time Calculation:

Formula:
The expected time (TE) can be calculated using the formula:
TE = (O + 4M + P) / 6

Given Data:
Optimistic time (O) = 2 minutes
Most likely time (M) = 5 minutes
Pessimistic time (P) = 8 minutes

Calculation:
TE = (2 + 4(5) + 8) / 6
TE = (2 + 20 + 8) / 6
TE = 30 / 6
TE = 5 minutes

Therefore, the expected time for the activity is 5 minutes.
Free Test
Community Answer
In a small engineering project, for an activity, the optimistic time...
Expected time
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer?
Question Description
In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer?.
Solutions for In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In a small engineering project, for an activity, the optimistic time is 2 minutes, the most likely time is 5 minutes and the pessimistic time is 8 minutes. What is the expected time of the activity?a) 1 minuteb) 5 minutesc) 8 minutesd) 18 minutesCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev