In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machine
costs 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman is
  • a)
    250
  • b)
    180
  • c)
    130
  • d)
    210
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
In the production shop of a company the breakdown of the machine is fo...
λ = 3/hr
μ = 4/hr
Total waiting time in system for one machine is
=  = 1 hour
The down time of 3 machines is
= 3 × 1 = 3 hour
Down time cost = 40 × 3 = Rs 120
Repairman cost = 3 × 20 = Rs 60
Total cost = 120 60 = Rs 180
View all questions of this test
Most Upvoted Answer
In the production shop of a company the breakdown of the machine is fo...
Given:
- Breakdown of machine follows Poisson distribution with an average rate of 3 machines per hour.
- Cost of breakdown time at one machine is 40 rupees per hour to the company.
- A repairman is hired who demands 20 rupees per hour.
- Repairman repairs the broken down machines following the exponential distribution at the rate of 4 per hour.

To find:
- Total cost involved in hiring the repairman.

Solution:
1. Expected number of breakdowns in an hour:
- The breakdown of the machine follows Poisson distribution with an average rate of 3 machines per hour.
- Therefore, the expected number of breakdowns in an hour is λ=3.

2. Cost of breakdown in an hour:
- Cost of breakdown time at one machine is 40 rupees per hour to the company.
- Therefore, the cost of breakdown in an hour is 40*λ=40*3=120 rupees.

3. Expected number of repairs in an hour:
- Repairman repairs the broken down machines following the exponential distribution at the rate of 4 per hour.
- Therefore, the expected number of repairs in an hour is μ=4.

4. Cost of repairs in an hour:
- Repairman demands 20 rupees per hour.
- Therefore, the cost of repairs in an hour is 20*μ=20*4=80 rupees.

5. Total cost involved in hiring the repairman:
- Total cost involved in hiring the repairman is the sum of the cost of breakdown and the cost of repairs in an hour.
- Total cost = 120 + 80 = 200 rupees.

Therefore, the correct option is (B) 180 rupees.
Free Test
Community Answer
In the production shop of a company the breakdown of the machine is fo...
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer?
Question Description
In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer?.
Solutions for In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer?, a detailed solution for In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice In the production shop of a company the breakdown of the machine is found to follow poisson distribution with an average rate of 3 machines per hour. Break down time at one machinecosts 40 rupees per hour to the company. The company hires a repairman who demands rupees 20 per hour and will repair the broken down machines following the exponential distribution at the rate of 4 per hour. The total cost involved in hiring the repairman isa)250b)180c)130d)210Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev