The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.
On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.
In the original timeline of the LHC commissioning, the first "modest" high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,
LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERN's 20 Member States, CERN officials, and members of the worldwide scientific community.
On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be "dumped" from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as "It's a great day to be a particle physicist". According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.
CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.
The results of the first proton-proton collisions at energies higher than Fermilab's Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).
 
Q. What didn’t happen in the incident on September 19, 2008?
  • a)
    A faulty electrical connection led to the loss of almost six tonnes of liquid helium.
  • b)
    The beam pipe lost vacuum conditions.
  • c)
    53 magnets had to be replaced because of faulty electrical conditions.
  • d)
    The effect was a temperature rise of about 100 kelvin in some of the affected magnets
Correct answer is option 'C'. Can you explain this answer?
Verified Answer
The first beam was circulated through the collider on the morning of 1...
Options 1,2 and 4 are supported by the passage- “On 19 September 2008, a quench occurred in about 100 bending magnets....the incident was indeed initiated by a faulty electrical connection.”.
The passage states that “A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.” Thus, not ALL of them were replaced as stated in option 3, some were also repaired. Hence, the correct answer is option 3.
View all questions of this test
Most Upvoted Answer
The first beam was circulated through the collider on the morning of 1...
Understanding the Incident on September 19, 2008
On September 19, 2008, a significant incident occurred at CERN's Large Hadron Collider (LHC). The question asks what did not happen during this event, specifically regarding the faulty electrical conditions and the impact on the magnets.
Key Events of the Incident
- A faulty electrical connection was identified as the main cause of the incident, leading to various consequences.
- The incident resulted in the loss of approximately six tonnes of liquid helium, which was vented into the tunnel.
- There was a loss of vacuum conditions in the beam pipe, indicating that the integrity of the collider's environment was compromised.
- A temperature rise of about 100 kelvin was observed in some of the affected magnets, demonstrating the thermal impact of the incident.
Reasons Why Option C is Correct
- The statement in option C claims that "53 magnets had to be replaced because of faulty electrical conditions."
- The truth is that while the incident did lead to damage in 53 magnets, they were either repaired or replaced during the winter shutdown, not solely because of the faulty electrical conditions.
- The problem stemmed from a faulty connection affecting the magnets, but the terminology "had to be replaced because of faulty electrical conditions" implies an immediate need for replacement due to the fault itself, which isn't entirely accurate.
Conclusion
Thus, while the incident indeed damaged magnets, the phrasing in option C does not accurately represent the sequence and nature of events, making it the correct answer to the question posed.
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.Which of the following cannot be said about the Higgs Boson from the passage?

The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.Which of the following cannot be substantiated by the passage?

Group QuestionA passage is followed by questions pertaining to the passage. Read the passage and answer the questions. Choose the most appropriate answer.The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.Whatprecise branch of science is associated with the above passage?

The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.Whatis the objective of the LHC?

The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.From the passage, we can conclude that

The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer?
Question Description
The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer?.
Solutions for The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer?, a detailed solution for The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer? has been provided alongside types of The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The first beam was circulated through the collider on the morning of 10 September 2008. CERN successfully fired the protons around the tunnel in stages, three kilometres at a time. The particles were fired in a clockwise direction into the accelerator and successfully steered around it at 10:28 local time. The LHC successfully completed its first major test: after a series of trial runs, two white dots flashed on a computer screen showing the protons travelled the full length of the collider. It took less than one hour to guide the stream of particles around its inaugural circuit. CERN next successfully sent a beam of protons in a counterclockwise direction, taking slightly longer at one and a half hours due to a problem with the cryogenics, with the full circuit being completed at 14:59.On 19 September 2008, a quench occurred in about 100 bending magnets in sectors 3 and 4, causing a loss of approximately six tonnes of liquid helium, which was vented into the tunnel, and a temperature rise of about 100 kelvin in some of the affected magnets. Vacuum conditions in the beam pipe were also lost. Shortly after the incident CERN reported that the most likely cause of the problem was a faulty electrical connection between two magnets, and that - due to the time needed to warm up the affected sectors and then cool them back down to operating temperature - it would take at least two months to fix it. Subsequently, CERN released a preliminary analysis of the incident on 16 October 2008, and a more detailed one on 5 December 2008. Both analyses confirmed that the incident was indeed initiated by a faulty electrical connection. A total of 53 magnets were damaged in the incident and were repaired or replaced during the winter shutdown.In the original timeline of the LHC commissioning, the first modest high-energy collisions at a center-of-mass energy of 900 GeV were expected to take place before the end of September 2008, and the LHC was expected to be operating at 10 TeV by the time of the official inauguration on 21 October 2008. However, due to the delay caused by the above- mentioned incident, the collider was not operational until November 2009. Despite the delay,LHC was officially inaugurated on 21 October 2008, in the presence of political leaders, science ministers from CERNs 20 Member States, CERN officials, and members of the worldwide scientific community.On 30 March 2010, LHC set a record for high-energy collisions, by colliding proton beams at a combined energy level of 7 TeV. The attempt was the third that day, after two unsuccessful attempts in which the protons had to be dumped from the collider and new beams had to be injected. The event was described by CERN Director General Rolf Heuer as Its a great day to be a particle physicist. According to a press release, CERN will run the LHC for 18-24 months with the objective of delivering enough data to the experiments to make significant advances across a wide range of physics channels.CERN scientists estimate that if the Standard Model is correct, a single Higgs boson may be produced every few hours. At this rate, it may take about two to three years to collect enough data to discover the Higgs boson unambiguously. Similarly, it may take one year or more before sufficient results concerning supersymmetric particles have been gathered to draw meaningful conclusions.The results of the first proton-proton collisions at energies higher than Fermilabs Tevatron proton-antiproton collisions have been published, yielding greater-than-predicted charged hadron production. The CMS paper reports that the increase in the production rate of charged hadrons when the center-of-mass energy goes from 0.9 TeV to 2.36 TeV exceeds the predictions of the theoretical models used in the analysis, with the excess ranging from 10% to 14%, depending upon which model is used. The charged hadrons were primarily mesons (kaons and pions).Q.What didnt happen in the incident on September 19, 2008?a)A faulty electrical connection led to the loss of almost six tonnes of liquidhelium.b)The beam pipe lost vacuum conditions.c)53 magnets had to be replaced because of faulty electrical conditions.d)The effect was a temperature rise of about 100 kelvin in some of the affected magnetsCorrect answer is option 'C'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev