CAT Exam  >  CAT Questions  >  The table given below gives the days required... Start Learning for Free
The table given below gives the days required by a worker to complete the task.
Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.
The following information about their working schedule is given below:
1. All of them start the tasks together on the same day and same time.
2. Anwar works for two days and takes rest on the third day and repeats this routine.
3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.
Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.
 
Q. How many days will Anwar actually work for (i.e., excluding the days on whjch he was resting)?
    Correct answer is '8'. Can you explain this answer?
    Verified Answer
    The table given below gives the days required by a worker to complete ...
    From solution to the second question of the set, Hamid and Anwar complete 4 units of Work B on the seventh day. So the two have utilized (4/11) part of the day.
    Therefore, (7/11)th part of the day will be utilized by them to finish some part of Work C.
    In a day, Hamid and Anwar complete 5 and 10 units of Work C respectively.
    On the the seventh day, Hamid and Anwar finish (7/11) x 15
    Workdone by the two on 8th day =15 units
    On 9th day , Hamid completed 5 units of the work.
    Workdone by the two on 10th and 11th day = 30 units The remaining part of the work = 60 - 9.5 - 50 0.5 units
    This will be completed by Hamid on 12th day.
    Of the three days, Anwar works for two days. So of 12 days, he works for 8 days.
    Answer: 8
    View all questions of this test
    Explore Courses for CAT exam

    Similar CAT Doubts

    Anjali, Bipasha, and Chitra visited an entertainment park that has four rides. Each ride lasts one hour and can accommodate one visitor at one point. All rides begin at 9 am and must be completed by 5 pm except for Ride-3, for which the last ride has to be completed by 1 pm. Ride gates open every 30 minutes, e.g. 10 am, 10:30 am, and so on. Whenever a ride gate opens, and there is no visitor inside, the first visitor waiting in the queue buys the ticket just before taking the ride. The ticket prices are Rs. 20, Rs. 50, Rs. 30 and Rs. 40 for Rides 1 to 4, respectively. Each of the three visitors took at least one ride and did not necessarily take all rides. None of them took the same ride more than once. The movement time from one ride to another is negligible, and a visitor leaves the ride immediately after the completion of the ride. No one takes a break inside the park unless mentioned explicitly.The following information is also known. Chitra never waited in the queue and completed her visit by 11 am after spending Rs. 50 to pay for the ticket(s). Anjali took Ride-1 at 11 am after waiting for 30 mins for Chitra to complete it. It was the only ride where Anjali waited. Bipasha began her first of three rides at 11:30 am. All three visitors incurred the same amount of ticket expense by 12:15 pm. The last ride taken by Anjali and Bipasha was the same, where Bipasha waited 30 mins for Anjali to complete her ride.Before standing in the queue for that ride, Bipasha took a 1-hour coffee break after completing her previous ride.How many rides did Anjali and Chitra take in total? Correct answer is '6'. Can you explain this answer?

    Top Courses for CAT

    The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer?
    Question Description
    The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer?.
    Solutions for The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
    Here you can find the meaning of The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer?, a detailed solution for The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer? has been provided alongside types of The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The table given below gives the days required by a worker to complete the task.Two tasks, Task 1 and Task 2, are to be completed. Task 1 consists Work A that is immediately followed by Work C. Task 2 consists Work B that is immediately followed by Work C. Task 1 is taken up by Abdul and Akram, while Task 2 is taken up by the remaining two workers. Work C needs to be done seperately for each task.The following information about their working schedule is given below:1. All of them start the tasks together on the same day and same time.2. Anwar works for two days and takes rest on the third day and repeats this routine.3. Abdul and Akram work for 2 days together after which Akram takes rest for one day and Abdul for next one day and this routine continues.Note: While answering the questions, if final answer is not an integer (e.g., 5.36) then enter the next smallest integer (i.e., 6) as your answer.Q.How many days will Anwar actually work for (i.e., excluding the dayson whjch he was resting)?Correct answer is '8'. Can you explain this answer? tests, examples and also practice CAT tests.
    Explore Courses for CAT exam

    Top Courses for CAT

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev