CAT Exam  >  CAT Questions  >  Group QuestionAnswer the following question b... Start Learning for Free
Group Question
Answer the following question based on the information given below.
The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.
The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..
For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.
Additional Information:
1. Number of hours of work put in by each student in each subject is a multiple of five.
2. No person puts in 0 (zero) hours of work in any subject.
3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.


 
Q. What could be the maximum number of hours of work put in by B in all the subjects taken together?
  • a)
    110
  • b)
    125
  • c)
    130
  • d)
    140
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
Group QuestionAnswer the following question based on the information g...
The representation using the above graphs makes interpretation of the data very cumbersome. Therefore, first convert the above data in the form of a table.
In case of Finance, A, B, C and F spend a total of 120 hours on the project, which corresponds to 80% of the time required for the project.
Thus, the total time required for the project is (120 x 100)/80 i.e. 150 hours. The total hours required for each subject (except Systems) can be similarly calculated.
Thus, D and E together spend 30 hours on the project in Finance.
Since each person's input in terms of number of hours is a multiple of 5, the time spent by D can be 5, 10, 15, 20 or 25. Correspondingly the time spent by E is 25, 20, 15, 10 or 5. Note that no person spends zero hours on a project in any particular subject.
Note that the time given per person is for the top 4 contributors (in terms of hours) for the project in a particular subject.
In Finance, the minimum time mentioned is for C and F (20 hours each).
Hence, the number of hours spent by D or E on Finance cannot be more than 20.
Thus, the number of hours spent by D on Finance is 10, 15 or 20. Correspondingly, the number of hours for E is 20, 15 or 10.
Now, it has been given that a person whose number of hours have not been mentioned does not put in the same hours as any other student whose input in terms of number of hours has been mentioned for that subject.
Since C and F have spent 20 hours each on the project in Finance, neither D nor E can spend 20 hours on this project.
Therefore, neither of them can spend 10 hours on this project as well. (This is because if one of them spends 10 hours, the other spends 20 hours, which is invalid.) Hence, both D and E spend 15 hours each on the project in Finance.
Similarly, the number of hours for each person in each subject can be filled up as shown in the table below.

For Systems, the percentage contribution of the top 4 students is not known. Therefore, the total number of hours required, and consequently, the number of hours put in by D and E cannot be calculated.
Input (in terms of hours) by B in Finance, Marketing and Systems is 30, 40 and 40 hours respectively.
B's maximum input in Human Resource as well as in Operations can be 15 hours each.
The maximum number of hours of work put in by B in total can be (30 + 40 + 15 + 15 + 40) = 140 hours.
Hence, option 4.
View all questions of this test
Explore Courses for CAT exam

Similar CAT Doubts

The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.Assume that the two students whose input is not mentioned for a subject put in equal efforts (in terms of hours) in that particular subject. If this is true for all five subjects, which student puts in maximum number of hours across all subjects?

The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the minimum number of hours of work put in by F?

The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.Which subject required the second highest number of hours?

Direction: Read the following passage and answer the question that follows:There are several key difficulties surrounding the topic of percentages. Research has shown that there has been one difficulty which is more common than others; the meaning of the terms ‘of’ and ‘out of’. Hansen (2011) states that both terms represent an operator which needs explaining. Teachers need to address these before the topic is introduced to stop any confusion. ‘Of’ represents the multiplication operator, for example: 60% of 70 means 0.6 multiplied by 70; ‘out of’ represents the division operator, for example 30 out of 50 means 30 divided by 50. The teaching of these terms needs to be clear prior to teaching, so that children are confident in what these terms represent.Killen and Hindhaugh (2018) believe that once children understand that 1/10 is equal to 10% they will be able to use their knowledge of fractions to determine other multiples of 10. For example; Find 40% of 200. If children are aware that 10% is 20, then it will become obvious to them that 40% must be 80. This method enlightens many other practical ways to find other percentages of a quantity. Once children know 10%, they may also start finding half percent’s, such as; 5% or 25%. However, Killen and Hindhaugh (2018) state that a difficulty could occur when they are asking for a percentage of a quantity. If children are being asked to find the percentage, they may believe that the answer is always in percent. For example; find 60% of £480. Children may be capable of calculating the answer of 288 but instead of writing down £288, they may write down 288%. Teachers will need to explain this issue and address to children that once calculating the answer, it must be in the same units as the given quantity.Hansen also comments that the key to succession in the understanding of percentages is the relationship and understanding the children have with fractions and decimals. For example: they should be aware that 50% is equivalent to ½ and 0.5, and 25% is equivalent to ¼ and 0.25. Teaching these topics in isolation of each other should be strictly avoided as this may destroy a child’s deep mathematical understanding. Killen and Hindhaugh agree with this as they noted that children need to continually link decimals, fractions and percentages to their knowledge of the number system and operations that they are familiar with. Reys, et al (2010) believes however that percentages are more closely linked with ratios and proportions in mathematics and how important it is for teachers to teach these other topics to a high level. This is to later reduce the amount of errors a child has over percentages. However, these theorists also agree that understanding percentages requires no more new skills or concepts beyond those used in identifying fractions, decimals, ratios and proportions. Reys, et al states that an effective way of starting these topics is to explore children’s basic knowledge of what percentage means to them.Barmby et al noted that a misconception occurs whenever a learner’s outlook of a task does not connect to the accepted meaning of the overall concept. Ryan and Williams state that it is more damaging for children to have misconceptions of mathematical concepts than difficulties calculating them. Killen and Hindhaugh begin to talk how the use of rules and recipes are commonly used more so by teachers that are not fully confident with percentages. The main point of the argument is that if children are taught these rules linked to percentages, misconceptions can occur. This could be caused if the child forgets or misapplies the rule to their working out.This method is not the most reliable for children but can be a quick alternative for teachers to teach their class, if they are not fully confident in the topic themselves. This links to one of the most common misconceptions in the primary classroom. Killen and Hindhaugh state that it is the teacher’s responsibility for their children’s successes in that subject area. If the teaching is effective, then the child will become more confident and develop more links revolving around the topic of percentages. This will result in the child having a high level of understanding. However, if the teaching is not up to standard the child may lose confidence in themselves and end up being confused with the simplest of questions.Q. On the basis of the information in the passage, all of the following are potential problems children might face when learning percentages EXCEPT that they

A drug peddler operated from four different locations to avoid the local police traps. He had named these places as Tea Stall, Coffee Stall, Milk Stall and Juice Stall. This drug peddler dealt in six different types of drugs: Cocaine, Heroin, Opium, Marijuana, Morphine and Darvon. To camouflage his operations he sold these drugs in pre-packed envelopes. Further to facilitate his operations he had got all of these drugs packed according to the order size. The different envelopes he used to denote different sizes were known as Chota, Medium, Bada, Vazir, and Badshah. Each of the drugs was available in all the sizes of envelopes.However an intelligent officer, Karamchand from Narcotics department received certain pieces of information from one of his sources, Lily. Before raiding on to the premises Karamchand decided to completely analyze the piece of information he had with him.The first chart gave the details of the number of envelopes mentioned as a percentage of the total number of envelopes.His second source, Liliput gave him additional information that the number of Vazir envelopes, as a percentage of total number of envelopes in each of the location, is not more than 1% in Coffee and Milk stall.His third source, Parma opined that all the envelopes containing one or the other of the three drugs - Cocaine, Heroin and Darvon - were only in one or the other of the three envelopes - Chota, Medium or Bada.Q.If the information from the 1st and 2nd source is considered, then what could be the minimum percentage of Vazir envelopes as compared to thetotal number of envelopes, which Karamchand could expect in Tea stall?

Top Courses for CAT

Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer?
Question Description
Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer? for CAT 2025 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for CAT 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer?.
Solutions for Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer?, a detailed solution for Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Group QuestionAnswer the following question based on the information given below.The following diagrams represent the total input (in terms of hours) that a group of six students is expected to put in for their project in five subjects, namely Finance, Marketing, HR, Operations and Systems.The four numbers inside the triangles represent the number of hours put in by four of the six students, who put in the maximum number of hours in the project in that particular subject. The percentage in the semi-circle expresses the number of hours put in by those four students for the project in that particular subject as a percentage of the total input (in hours) required for that subject..For example, out of the total number of hours required by the project in Finance, A puts in 50 hours of work, B puts in 30 hours of work, C puts in 20 hours of work and F puts in 20 hours of work. Also A, B, C and F put in 80% of the total input required, in terms of hours. D and E together put in the remaining 20%. This percentage information for the proportion of input put in by the four students in the project in Systems has been intentionally removed.Additional Information:1. Number of hours of work put in by each student in each subject is a multiple of five.2. No person puts in 0 (zero) hours of work in any subject.3. A student whose number of hours of work for a particular subject is not mentioned did not put in the same hours as any other student whose input in terms of hours is mentioned for that subject.Q.What could be the maximum number of hours of work put in by B in all the subjects taken together?a)110b)125c)130d)140Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev