Defence Exam  >  Defence Questions  >  A and B working together can finish a piece o... Start Learning for Free
A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?
  • a)
    18 days 
  • b)
    20 days 
  • c)
    24 days 
  • d)
    25 days
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A and B working together can finish a piece of work in 12 days while B...
Let total units of work = 60 units (LCM of 12 and 30)
∴ Efficiency of (A + B) = 60/12 = 5
And Efficiency of B = 60/30 = 2
∴ Efficiency of A = 5 – 2 = 3
∴ Time taken by A alone to finish the work = 60/3 = 20 days
View all questions of this test
Most Upvoted Answer
A and B working together can finish a piece of work in 12 days while B...
To solve this problem, we can use the concept of work rates. Let's denote the work rate of A as "a" (meaning A can complete "a" units of work per day) and the work rate of B as "b" (meaning B can complete "b" units of work per day).

We are given that A and B can finish the work together in 12 days, so their combined work rate is 1/12 of the work per day. This can be expressed as:
1/12 = a + b

We are also given that B alone can finish the work in 30 days, so B's work rate is 1/30 of the work per day. This can be expressed as:
1/30 = b

Now we have two equations with two unknowns (a and b). We can solve this system of equations to find the values of a and b.

Solving the second equation for b, we have:
b = 1/30

Substituting this value of b into the first equation, we have:
1/12 = a + 1/30

To simplify the equation, we can find a common denominator of 12 and 30, which is 60. Multiplying both sides of the equation by 60, we get:
5 = 60a + 2

Subtracting 2 from both sides of the equation, we have:
3 = 60a

Dividing both sides of the equation by 60, we get:
a = 3/60 = 1/20

Therefore, A's work rate is 1/20 of the work per day, meaning A can complete 1/20 of the work in one day. To find out how many days it will take for A to complete the work alone, we can invert A's work rate:
1 day = 1/20 of the work
20 days = 1 work

So, A alone can finish the work in 20 days. Therefore, the correct answer is option B.
Explore Courses for Defence exam
A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer?
Question Description
A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer? for Defence 2024 is part of Defence preparation. The Question and answers have been prepared according to the Defence exam syllabus. Information about A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Defence 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer?.
Solutions for A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Defence. Download more important topics, notes, lectures and mock test series for Defence Exam by signing up for free.
Here you can find the meaning of A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A and B working together can finish a piece of work in 12 days while B alone can finish it in 30 days. In how many days can A alone finish the work?a)18 daysb)20 daysc)24 daysd)25 daysCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Defence tests.
Explore Courses for Defence exam
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev