CAT Exam  >  CAT Questions  >  A contractor undertakes to dig a canal 10 km ... Start Learning for Free
A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?
  • a)
    10
  • b)
    20
  • c)
    25
  • d)
    15
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
A contractor undertakes to dig a canal 10 km long in 180 days and empl...
In 60 days 40 men completed 2.5 km of the canal.
Let x number of men be required to complete 10 - 2.5 = 7.5 km of the canal in 180 - 60 = 120 days.
M1 xD1 x W2 = M2 x D2 x W1 
60 x 40 x 7.5 = x x 120 x 2.5
x = 60 men
So the contractor requires 60 - 40 = 20 more men to complete the work on the scheduled time.
Hence, option 2.
View all questions of this test
Most Upvoted Answer
A contractor undertakes to dig a canal 10 km long in 180 days and empl...
Given information:
- Length of the canal to be dug: 10 km
- Time allocated for the work: 180 days
- Number of men employed: 40
- After 60 days, only 2.5 km of the canal has been completed

To find:
- How many more men does the contractor need to employ in order to complete the work on time?

Calculation:
1. First, we need to find the rate at which work is being done by the current number of men.
- In 60 days, the work completed is 2.5 km.
- Therefore, the rate of work is 2.5 km/60 days = 1/24 km per day.

2. Now, let's find the total work remaining to be done.
- Total length of the canal to be dug = 10 km
- Work completed so far = 2.5 km
- Therefore, work remaining = 10 km - 2.5 km = 7.5 km.

3. Next, we calculate the number of days required to complete the remaining work at the current rate of work.
- Rate of work = 1/24 km per day
- Work remaining = 7.5 km
- Number of days required = (7.5 km) / (1/24 km per day) = 7.5 x 24 = 180 days

Analysis:
- The calculation shows that at the current rate of work, the contractor will need the full 180 days to complete the remaining 7.5 km of the canal.

To complete the work on time, the contractor needs to increase the number of men. Let's calculate how many more men are required.

4. We know that the total work remaining is 7.5 km, and the contractor wants to complete it in the remaining 120 days (180 days - 60 days).

- Work remaining = 7.5 km
- Time remaining = 120 days
- Rate of work required = Work remaining / Time remaining = 7.5 km / 120 days = 1/16 km per day

5. Now, let's calculate the number of men required to achieve the desired rate of work.
- Rate of work per man = 1/24 km per day
- Desired rate of work = 1/16 km per day
- Number of men required = (Desired rate of work) / (Rate of work per man) = (1/16) / (1/24) = 24/16 = 3/2

Therefore, the contractor needs to increase the number of men by 3/2 or 1.5.

Final Answer:
- The contractor needs to increase the number of men by 1.5, which is equivalent to 1.5 x 40 = 60.
- Therefore, the contractor needs to increase the number of men by 60 to complete the work on time.

The correct answer is option (B) 20.
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Similar CAT Doubts

A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer?
Question Description
A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer?.
Solutions for A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer?, a detailed solution for A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A contractor undertakes to dig a canal 10 km long in 180 days and employs 40 men. After 60 days he finds that only 2.5 km of the canal has been completed. To complete the work on the scheduled time how many men does he have to increase?a)10b)20c)25d)15Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev