4 men and 6 women can complete a work in 8 days, while 3 men and 7 wom...
Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.
hen, 4x + 6y =1/8 and 3x + 7y =1/10
Solving the two equations, we get: x = 11/400 , y = 1/400
∴ 1 woman's 1 day's work = 1/400
10 women's 1 day's work =
Hence, 10 women will complete the work in 40 days.
View all questions of this test
4 men and 6 women can complete a work in 8 days, while 3 men and 7 wom...
Given:
- 4 men and 6 women can complete the work in 8 days.
- 3 men and 7 women can complete the work in 10 days.
Let's assume that the work requires x days for 1 man to complete and y days for 1 woman to complete.
Calculation:
- In 1 day, 1 man can complete 1/x of the work and 1 woman can complete 1/y of the work.
- Therefore, in 1 day, 4 men can complete 4/x of the work and 6 women can complete 6/y of the work.
- According to the first statement, 4 men and 6 women can complete the work in 8 days.
- So, in 1 day, 4 men and 6 women can complete 1/8 of the work.
From the above calculations, we can form the following equation:
4/x + 6/y = 1/8 .............(1)
- Similarly, in 1 day, 3 men can complete 3/x of the work and 7 women can complete 7/y of the work.
- According to the second statement, 3 men and 7 women can complete the work in 10 days.
- So, in 1 day, 3 men and 7 women can complete 1/10 of the work.
From the above calculations, we can form the following equation:
3/x + 7/y = 1/10 .............(2)
Now, we need to solve equations (1) and (2) to find the values of x and y.
Solving these equations simultaneously, we get:
x = 16 days and y = 28 days
Explanation:
- This means that 1 man can complete the work in 16 days and 1 woman can complete the work in 28 days.
- We need to find how many days 10 women will take to complete the work.
- In 1 day, 10 women can complete 10/y of the work.
- Substituting the value of y, we get:
10/28 = 5/14
Therefore, 10 women will take 14/5 days to complete the work.
Converting this to the nearest whole number, we get:
14/5 ≈ 2.8
So, 10 women will take approximately 3 days to complete the work.
Hence, the correct answer is option (A) 40 days.
4 men and 6 women can complete a work in 8 days, while 3 men and 7 wom...
My answer is 16 days. something error in the following options