Squaring of sleepers through packing consists of
  • a)
    Adjusting the sleepers to be perpendicular to the rails
  • b)
    Adjusting the ballast under sleepers to space them parallel to each other
  • c)
    Cutting the edges of the sleepers to a square shape
  • d)
    Adjusting the rails to be perpendicular to the sleepers
Correct answer is option 'B'. Can you explain this answer?
Verified Answer
Squaring of sleepers through packing consists ofa)Adjusting the sleepe...
In through packing the sleepers are squared and brought to specified spacing at straight lengths and on curves i.e., the ballast under the sleepers is adjusted to space them parallel to each other.
View all questions of this test
Most Upvoted Answer
Squaring of sleepers through packing consists ofa)Adjusting the sleepe...
Explanation:

Squaring of sleepers through packing refers to the process of adjusting the ballast under sleepers to space them parallel to each other. This is done to ensure the stability and proper alignment of the railway tracks. Let's break down the options given and understand why option 'B' is the correct answer:

a) Adjusting the sleepers to be perpendicular to the rails:
While it is important to have the sleepers perpendicular to the rails, this is not a part of squaring the sleepers through packing. The orientation of the sleepers is typically determined during the construction or installation process and is not altered through packing.

b) Adjusting the ballast under sleepers to space them parallel to each other:
This option is the correct answer. Squaring of sleepers through packing involves adjusting the ballast, which is the layer of material (usually crushed stones) that provides support and stability to the sleepers. By adding or removing ballast and adjusting its distribution, the sleepers can be spaced parallel to each other, ensuring a straight and well-aligned track.

c) Cutting the edges of the sleepers to a square shape:
This option is not related to squaring of sleepers through packing. Cutting the edges of the sleepers to a square shape is a separate process that may be done during the manufacturing or maintenance of the sleepers, but it does not directly contribute to the squaring of sleepers through packing.

d) Adjusting the rails to be perpendicular to the sleepers:
Similar to option 'a', adjusting the rails to be perpendicular to the sleepers is not a part of squaring the sleepers through packing. The alignment between the rails and sleepers is typically established during the track laying process and is not altered through packing.

In conclusion, the correct answer is option 'B' because squaring of sleepers through packing involves adjusting the ballast under sleepers to space them parallel to each other, ensuring a well-aligned track.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer?
Question Description
Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer?.
Solutions for Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer?, a detailed solution for Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer? has been provided alongside types of Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Squaring of sleepers through packing consists ofa)Adjusting the sleepers to be perpendicular to the railsb)Adjusting the ballast under sleepers to space them parallel to each otherc)Cutting the edges of the sleepers to a square shaped)Adjusting the rails to be perpendicular to the sleepersCorrect answer is option 'B'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev