If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as the
  • a)
    Mean of the values for 5 mm and 2.5 mm penetration
  • b)
    Higher value minus the lower value
  • c)
    Lower value corresponding to 2.5 mm penetration
  • d)
    Higher value obtained at 5 mm penetration
Correct answer is option 'D'. Can you explain this answer?
Verified Answer
If the CBR value obtained at 5 mm penetration is higher than that at 2...
The average CBR value of three test specimens is reported to the first decimal place, as the GBR value of the test specimen. If the maximum variation' iii the CBR values of these specimens exceeds specified limits (3% for CB  up to 10% to 5% for CBR 10 to 30% and 10% for CBR 30-60%), then the design CBR should be the average of at least six specimens.
View all questions of this test
Most Upvoted Answer
If the CBR value obtained at 5 mm penetration is higher than that at 2...
Explanation:

CBR (California Bearing Ratio) test is used to determine the strength of the subgrade soil and the base course material for designing the pavement thickness. The test involves penetrating a plunger into the soil at a constant rate of penetration and measuring the force required to penetrate the soil at different depths. The ratio of the force required to penetrate the soil to the force required to penetrate a standard crushed rock material at the same depth is known as the CBR value.

If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking. The aim of the repeated test is to ensure the consistency and accuracy of the CBR value. If the check test reveals a similar trend, then the CBR value is to be reported as the higher value obtained at 5 mm penetration.

The reason for reporting the higher value obtained at 5 mm penetration is that the CBR value at 5 mm penetration is considered more critical than that at 2.5 mm penetration. This is because the thickness of the asphalt layer in a pavement design is usually greater than 5 mm. Therefore, the CBR value at 5 mm penetration is more relevant for designing the pavement thickness.

To summarize:

- CBR test is used to determine the strength of the subgrade soil and the base course material for designing the pavement thickness.
- If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking.
- If the check test reveals a similar trend, then the CBR value is to be reported as the higher value obtained at 5 mm penetration.
- The CBR value at 5 mm penetration is considered more critical than that at 2.5 mm penetration for designing the pavement thickness.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer?
Question Description
If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer?.
Solutions for If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer?, a detailed solution for If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer? has been provided alongside types of If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If the CBR value obtained at 5 mm penetration is higher than that at 2.5 mm, then the test is repeated for checking: and if the check test reveals a. similar trend, then the CBR value is to be reported as thea)Mean of the values for 5 mm and 2.5 mm penetrationb)Higher value minus the lower valuec)Lower value corresponding to 2.5 mm penetrationd)Higher value obtained at 5 mm penetrationCorrect answer is option 'D'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev