When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as?
Most Upvoted Answer
When recurring investment made at different periods of time are brough...
Present Worth Analysis
Present Worth Analysis is a financial evaluation method used to compare the value of different cash flows that occur at different times. It allows for the assessment of recurring investments by converting them into a single equivalent value at a specific point in time, typically the beginning of the project.
Key Concepts
- Time Value of Money: This principle recognizes that a dollar today is worth more than a dollar in the future. Therefore, future cash flows need to be discounted back to their present value for accurate comparison.
- Discount Rate: This is the interest rate used to calculate the present value of future cash flows. It reflects the opportunity cost of capital and the risk associated with the investment.
- Equivalent Annual Annuity (EAA): In some cases, it may be beneficial to express recurring investments as an equivalent annual payment. This standardizes cash flows, making them easier to compare.
Application in Civil Engineering
- Project Evaluation: Present Worth Analysis is commonly used in civil engineering for evaluating the economic feasibility of projects. It helps engineers and decision-makers understand the financial implications of different investment options over time.
- Comparative Analysis: By converting all cash flows to present value, engineers can compare projects with different cash flow patterns and durations, helping to identify the most financially viable option.
Conclusion
In summary, Present Worth Analysis is essential for assessing investments with varying cash flow schedules. By applying the time value of money and calculating present values, it provides a clear framework for making informed financial decisions in civil engineering projects.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as?
Question Description
When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as? for Civil Engineering (CE) 2025 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as? covers all topics & solutions for Civil Engineering (CE) 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as?.
Solutions for When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as? defined & explained in the simplest way possible. Besides giving the explanation of When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as?, a detailed solution for When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as? has been provided alongside types of When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as? theory, EduRev gives you an ample number of questions to practice When recurring investment made at different periods of time are brought back to equivalent made at beginning of project it is termed as? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev