CAT Exam  >  CAT Questions  >  Sixty-for men working 8 hrs a day plan to com... Start Learning for Free
Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?
  • a)
    11
  • b)
    12
  • c)
    13
  • d)
    15
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
Sixty-for men working 8 hrs a day plan to complete a piece of work in ...

  ► 40% work in 40h → 60% work in 60h.
  ► Hence, working hours = 60 / 4 = 15 h
View all questions of this test
Most Upvoted Answer
Sixty-for men working 8 hrs a day plan to complete a piece of work in ...
Given data:
- 60 men plan to complete a piece of work in 9 days working 8 hrs a day
- After 5 days, they found that they had completed only 40% of the work
- They now want to finish the remaining portion of the work in 4 more days
- We need to find how many hours per day they need to work to achieve the target

Calculations:
- Let the total work be W
- Work completed in the first 5 days = 40% of W = 0.4W
- Remaining work = W - 0.4W = 0.6W
- Days left to complete the remaining work = 4
- Total days to complete the entire work = 9 + 5 = 14
- Total work done in 14 days = 60 x 8 x 14 = 6720 man-hours
- Work done in the first 5 days = 60 x 8 x 5 = 2400 man-hours
- Work remaining to be done in the last 4 days = 0.6W
- Work done in the first 5 days + work remaining to be done = total work
- 2400 + 0.6W = 6720
- 0.6W = 4320
- W = 7200
- Work to be done in the last 4 days = 0.6W = 4320
- Man-hours required per day in the last 4 days = 4320 / (60 x 4) = 18
- Hours per day per man in the last 4 days = 18 / 60 = 0.3

Answer:
- The men need to work for 0.3 hours per day or 18 minutes per day to achieve the target
- Converting minutes to hours, the answer is 0.3 x 60 = 18/60 = 0.3 hours per day
- Rounded to the nearest integer, the answer is 0.3 x 60 = 18 minutes per day, which is closest to option A, i.e., 11 hours.
Free Test
Community Answer
Sixty-for men working 8 hrs a day plan to complete a piece of work in ...
They completed 40% in 5 days.
with this speed they will take 7.5 days to complete the remaining 60% by working 8 hours in a day. but we need to complete it in 4 days.

so 7.5 days - 8 hours a day
then 8 days - 7.5 hours a day
then 4 days - 15 hours.

'D' is the correct answer.
Explore Courses for CAT exam

Top Courses for CAT

Question Description
Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer? for CAT 2025 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for CAT 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer?.
Solutions for Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer?, a detailed solution for Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Sixty-for men working 8 hrs a day plan to complete a piece of work in 9 days. However, 5 days later they found that they had completed only 40% of the work. They now wanted to finish the remaining portion of the work in 4 more days. How many hours per day should they need to work in order to achieve the target?a)11b)12c)13d)15Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev