Consider the following statements regarding AON diagram:
1. Each activity is represented by a circle.
2. The successor of the activity is connected by a directed arrow.
3. The number of the activity and the amount of time required for its completion are inserted in the job node.
4. An AON network contains a node for the start and a node for a finish of the project.
Which of these statements are correct?
  • a)
    1, 2 and 3
  • b)
    2, 3 and 4
  • c)
    1,3 and 4
  • d)
    1,2, and 4
Correct answer is option 'C'. Can you explain this answer?
Most Upvoted Answer
Consider the following statements regarding AON diagram:1. Each activi...
AON Diagram:

An Activity on Node (AON) diagram is a graphical representation of a project schedule. It is used to show the sequence of activities needed to complete a project, their durations, and the dependencies between them.

Statements:

1. Each activity is represented by a circle.
2. The successor of the activity is connected by a directed arrow.
3. The number of the activity and the amount of time required for its completion are inserted in the job node.
4. An AON network contains a node for the start and a node for a finish of the project.

Correct Statements:

a) 1, 2 and 3
b) 2, 3 and 4
c) 1, 3 and 4
d) 1, 2, and 4

Correct answer is option 'C' (1, 3, and 4).

Explanation:

1. Each activity is represented by a circle:
This statement is correct. In an AON diagram, each activity is represented by a circle or node.

2. The successor of the activity is connected by a directed arrow:
This statement is correct. In an AON diagram, the successor of an activity is connected by a directed arrow to show the sequence of activities.

3. The number of the activity and the amount of time required for its completion are inserted in the job node:
This statement is correct. In an AON diagram, the number of the activity and the amount of time required for its completion are inserted in the job node.

4. An AON network contains a node for the start and a node for a finish of the project:
This statement is incorrect. An AON network does not contain a node for the start and a node for a finish of the project. Instead, it contains a node for the start and a node for the end of each activity sequence.

Therefore, the correct statements are 1, 3, and 4.
Free Test
Community Answer
Consider the following statements regarding AON diagram:1. Each activi...
From my point of view the answer will be option B
Because in AON every activity defined via rectangular box
Explore Courses for Civil Engineering (CE) exam

Similar Civil Engineering (CE) Doubts

Top Courses for Civil Engineering (CE)

Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer?
Question Description
Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer? for Civil Engineering (CE) 2024 is part of Civil Engineering (CE) preparation. The Question and answers have been prepared according to the Civil Engineering (CE) exam syllabus. Information about Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Civil Engineering (CE) 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer?.
Solutions for Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Civil Engineering (CE). Download more important topics, notes, lectures and mock test series for Civil Engineering (CE) Exam by signing up for free.
Here you can find the meaning of Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer?, a detailed solution for Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the following statements regarding AON diagram:1. Each activity is represented by a circle.2. The successor of the activity is connected by a directed arrow.3. The number of the activity and the amount of time required for its completion are inserted in the job node.4. An AON network contains a node for the start and a node for a finish of the project.Which of these statements are correct?a)1, 2 and 3b)2, 3 and 4c)1,3 and 4d)1,2, and 4Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Civil Engineering (CE) tests.
Explore Courses for Civil Engineering (CE) exam

Top Courses for Civil Engineering (CE)

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev