The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.
  • a)
    F − C − G − E − D − B − A, 2
  • b)
    A − B − D − E − G − C − F, 2
  • c)
    F − C − G − E − A − B − D, 3
  • d)
    A − B − D − F − C − G − E, 4
Correct answer is option 'A'. Can you explain this answer?
Most Upvoted Answer
The todays date in a production calendar of an industry is 175. Seque...
Jobs should be arranged in the increasing order of critical ratio.
Sequence: F − C − G − E − D − B − A
Number of jobs behind schedule = no. of jobs whose critical ratio is less than 1
i.e., C & F in this case
∴ Number of jobs = 2
Free Test
Community Answer
The todays date in a production calendar of an industry is 175. Seque...
Jobs should be arranged in the increasing order of critical ratio.
Sequence: F − C − G − E − D − B − A
Number of jobs behind schedule = no. of jobs whose critical ratio is less than 1
i.e., C & F in this case
∴ Number of jobs = 2
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Question Description
The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer?.
Solutions for The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer?, a detailed solution for The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The todays date in a production calendar of an industry is 175. Sequence the jobs listed below by critical ratio rule and also find the number of jobs that are behind the schedule.a) F − C − G − E − D − B − A, 2b) A − B − D − E − G − C − F, 2c) F − C − G − E − A − B − D, 3d) A − B − D − F − C − G − E, 4Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev