The lead time and consumption pattern of a component is as follows:
If safety stock = 54,000 units. The ROL is
  • a)
    2,50,000
  • b)
    3,00,000
  • c)
    2,46,000
  • d)
    2,40,000
Correct answer is option 'B'. Can you explain this answer?
Most Upvoted Answer
The lead time and consumption pattern of a component is as follows:If...
Average lead time
= 0.2 × 15 + 0.5 × 20 + 0.3 × 25
= 20.5
Average consumption
= 0.5 × 10,000 + 0.5 × 14,000
= 12,000 units
ROL = SS + Avg. lead time × Avg. consumption
= 54,000 + 20.5 × 12,000
= 3,00,000
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Question Description
The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer? for Mechanical Engineering 2025 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2025 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer?.
Solutions for The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer?, a detailed solution for The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer? has been provided alongside types of The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The lead time and consumption pattern of a component is as follows:If safety stock = 54,000 units. The ROL isa) 2,50,000b) 3,00,000c) 2,46,000d) 2,40,000Correct answer is option 'B'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev