Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   A PERT network is shown below. Find the stan... Start Learning for Free
A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)
  • a)
    2.3
  • b)
    2.6
Correct answer is between ' 2.3, 2.6'. Can you explain this answer?
Verified Answer
A PERT network is shown below. Find the standard deviation of critica...
Paths:
1‐ 2‐ 3‐ 7 = 9 + 5 + 11 = 25∗
1‐ 5‐ 7 = 16 + 8 = 24
1‐ 4‐ 7 = 9 + 4 = 13
standard Deviation of critical path
= 2.45
View all questions of this test
Most Upvoted Answer
A PERT network is shown below. Find the standard deviation of critica...
Paths:
1‐ 2‐ 3‐ 7 = 9 + 5 + 11 = 25∗
1‐ 5‐ 7 = 16 + 8 = 24
1‐ 4‐ 7 = 9 + 4 = 13
standard Deviation of critical path
= 2.45
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer?
Question Description
A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer?.
Solutions for A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer?, a detailed solution for A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer? has been provided alongside types of A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A PERT network is shown below. Find the standard deviation of critical path (Upto 2 decimal places)a) 2.3b) 2.6Correct answer is between ' 2.3, 2.6'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev