Mechanical Engineering Exam  >  Mechanical Engineering Questions  >  A PERT network has 9 activities on its critic... Start Learning for Free
A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.
  • a)
    27  
  • b)
    81  
  • c)
    3  
  • d)
Correct answer is option 'D'. Can you explain this answer?
Most Upvoted Answer
A PERT network has 9 activities on its critical path. The standard dev...
Activities along critical path = 9
Standard deviation of each activity is 3
SD along critical path = 

Hence, the correct option is (D). 
Free Test
Community Answer
A PERT network has 9 activities on its critical path. The standard dev...
The standard deviation of the critical path in a PERT network can be found by summing the variances of the activities on the critical path and then taking the square root of the sum. Since the standard deviation of each activity on the critical path is given as 3, we can find the standard deviation of the critical path as follows:

1. Find the variance of each activity:
- The variance of an activity is equal to the square of its standard deviation.
- Since the standard deviation of each activity on the critical path is 3, the variance of each activity is 3^2 = 9.

2. Sum the variances of all activities on the critical path:
- Since there are 9 activities on the critical path, the sum of their variances is 9 + 9 + 9 + 9 + 9 + 9 + 9 + 9 + 9 = 81.

3. Take the square root of the sum of variances:
- The standard deviation of the critical path is equal to the square root of the sum of variances, which is the square root of 81.
- Taking the square root of 81 gives us the standard deviation of the critical path as 9.

Therefore, the correct answer is option 'D' - 9.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer?
Question Description
A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer?.
Solutions for A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer?, a detailed solution for A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer? has been provided alongside types of A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice A PERT network has 9 activities on its critical path. The standard deviation of each activity on critical path is 3. The standard deviation of critical path is_________.a)27 b)81 c)3 d)9Correct answer is option 'D'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev