Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   Consider the network shown in figure. The th... Start Learning for Free
Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project is
Ans. A
  • a)
    2.08
  • b)
    3.16
  • c)
    4.81
  • d)
    5.3
Correct answer is option ''. Can you explain this answer?
Verified Answer
Consider the network shown in figure. The three time estimates for ac...
Hence critical path is 1-2-3-4-5-6 Standard deviation is σ
View all questions of this test
Most Upvoted Answer
Consider the network shown in figure. The three time estimates for ac...
Understanding Project Time Estimates
In project management, each activity is associated with three time estimates: optimistic (a), pessimistic (b), and most likely (m). These estimates help in determining the expected duration and standard deviation of the project.
Calculating Standard Deviation
The standard deviation (σ) of an activity can be calculated using the formula:
σ = (b - a) / 6
Where:
- a = Optimistic time estimate
- b = Pessimistic time estimate
Steps for Calculation
- Identify the Time Estimates:
- Gather the optimistic (a), pessimistic (b), and most likely (m) estimates for each activity in the network.
- Apply the Formula:
- For each activity, calculate the standard deviation using the formula provided.
- Aggregate Standard Deviations:
- If the project consists of multiple activities, determine which activities are on the critical path and sum their variances (σ²).
- Calculate Overall Standard Deviation:
- The overall standard deviation of the project is the square root of the total variance.
Choosing the Correct Answer
After applying the above calculations, if you arrive at a standard deviation of approximately 2.08, 3.16, 4.81, or 5.3, compare it to your computed value.
If your calculations confirm a standard deviation of 2.08, then the correct answer is option "a".
Conclusion
Understanding how to calculate the standard deviation of a project is crucial for risk management and scheduling. Make sure to accurately gather and apply the time estimates to achieve the correct result.
Free Test
Community Answer
Consider the network shown in figure. The three time estimates for ac...
Hence critical path is 1-2-3-4-5-6 Standard deviation is σ
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer?
Question Description
Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer?.
Solutions for Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer?, a detailed solution for Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer? has been provided alongside types of Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the network shown in figure. The three time estimates for activities are given along the arrows. Then the standard deviation of the project isAns. Aa) 2.08b) 3.16c) 4.81d) 5.3Correct answer is option ''. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev