Question Description
DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared
according to
the CAT exam syllabus. Information about DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer?.
Solutions for DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT.
Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer?, a detailed solution for DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer? has been provided alongside types of DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.If, due to bad weather, a time gap of at least three hours is needed between every two successive polishings of an item, then what is the least total time required for polishing of the item? (in hours, in numerical value)Correct answer is '22'. Can you explain this answer? tests, examples and also practice CAT tests.