DIRECTIONS for the question: Go through the graph and the information given below and answer the question that follows.
In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.
Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?
  • a)
    7:00 am on the next day
  • b)
    8:00 am on the next day
  • c)
    4:00 pm on the same day
  • d)
    9:00 am on the next day
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
DIRECTIONS for the question:Go through the graph and the information g...
Let us first make a list of the timings in a day when a particular machine works. The letters in each box represents the time period.

The polishing will be completed by the earliest time. If the sequence in d → n → h, in which case, it will be completed by 7:00 am on the next day.
View all questions of this test
Most Upvoted Answer
DIRECTIONS for the question:Go through the graph and the information g...
Let us first make a list of the timings in a day when a particular machine works. The letters in each box represents the time period.

The polishing will be completed by the earliest time. If the sequence in d → n → h, in which case, it will be completed by 7:00 am on the next day.
Free Test
Community Answer
DIRECTIONS for the question:Go through the graph and the information g...
Analysis:
The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish.

Given Information:
- Each machine has a specific polish time and rest time.
- Each unit of item X needs to be polished exactly thrice on three different machines.
- There should be a time gap of at least two hours between two successive polishings of a unit.

Calculation:
- The earliest time for completion can be calculated by adding the total polish time and rest time for each machine.
- Machine A takes 3 hours for polishing and 3 hours of rest time, totaling 6 hours.
- Machine B takes 2 hours for polishing and 1 hour of rest time, totaling 3 hours.
- Machine C takes 3 hours for polishing and 1 hour of rest time, totaling 4 hours.
- Machine D takes 1 hour for polishing and 2 hours of rest time, totaling 3 hours.
- Machine E takes 2 hours for polishing and 2 hours of rest time, totaling 4 hours.
- Machine F takes 4 hours for polishing and 2 hours of rest time, totaling 6 hours.
Adding the total time for each machine, we get:
6 + 3 + 4 + 3 + 4 + 6 = 26 hours
Given that the polishing starts at 9:00 am, the earliest time by which the polishing will be completed is 26 hours later, which is 7:00 am on the next day.
Therefore, the correct answer is option 'A' - 7:00 am on the next day.
Attention CAT Students!
To make sure you are not studying endlessly, EduRev has designed CAT study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in CAT.
Explore Courses for CAT exam

Top Courses for CAT

DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer?
Question Description
DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer? for CAT 2024 is part of CAT preparation. The Question and answers have been prepared according to the CAT exam syllabus. Information about DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer? covers all topics & solutions for CAT 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer?.
Solutions for DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for CAT. Download more important topics, notes, lectures and mock test series for CAT Exam by signing up for free.
Here you can find the meaning of DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer?, a detailed solution for DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer? has been provided alongside types of DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice DIRECTIONS for the question:Go through the graph and the information given below and answer the question that follows.In a factory there are six polishing machines - A, B, C, D, E and F. The factory produces item X. Polishing is the last step of manufacturing process. Each of the machines A, B, C, D, E and F takes 3, 2, 3, 1, 2 and 4 hours respectively to polish one unit of X, which is called one polish time. After polishing each unit the machines need a rest of 3, 1, 1, 2, 2 and 2 hours respectively. Every machine starts polishing at 6.00 a.m. and no machine works after 4.00 p.m. Each unit of item X needs to be polished exactly thrice. These three polishing should be done on three different machines. There should be a time gap of at least two hours between two successive polishings of a unit. The total time taken for an item to be polished is the time taken from the starting of the first polish to the end of the third polish. No polish time has any break in between. No machine takes more or less time than the stipulated rest time between two consecutive polishings in a day.Q. If the polishing of an item is started at 9:00 am on a day, then what is the earliest time by which the polishing will be completed?a)7:00 am on the next dayb)8:00 am on the next dayc)4:00 pm on the same dayd)9:00 am on the next dayCorrect answer is option 'A'. Can you explain this answer? tests, examples and also practice CAT tests.
Explore Courses for CAT exam

Top Courses for CAT

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev