Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?
(A)9670
(B)9690
    Correct answer is between ','. Can you explain this answer?
    Verified Answer
    Consider the data of a project. If the indirect cost per week is Rs.1...
    Draw a network diagram for given data and find the critical path.
    Crash the critical activity 1-3 for 2 weeks.
    ∴ Total cost = Total normal cost +Indirect cost + slope cost − decrease in Indirect cost
    = 5900 + 4000 + [50 × 2] − [160 × 2]
    Total cost = 5900 + 4000 + 100 − 380 = Rs. 9680
    View all questions of this test
    Most Upvoted Answer
    Consider the data of a project. If the indirect cost per week is Rs.1...
    Draw a network diagram for given data and find the critical path.
    Crash the critical activity 1-3 for 2 weeks.
    ∴ Total cost = Total normal cost +Indirect cost + slope cost − decrease in Indirect cost
    = 5900 + 4000 + [50 × 2] − [160 × 2]
    Total cost = 5900 + 4000 + 100 − 380 = Rs. 9680
    Free Test
    Community Answer
    Consider the data of a project. If the indirect cost per week is Rs.1...
    Draw a network diagram for given data and find the critical path.
    Crash the critical activity 1-3 for 2 weeks.
    ∴ Total cost = Total normal cost +Indirect cost + slope cost − decrease in Indirect cost
    = 5900 + 4000 + [50 × 2] − [160 × 2]
    Total cost = 5900 + 4000 + 100 − 380 = Rs. 9680
    Attention Mechanical Engineering Students!
    To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer?
    Question Description
    Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer?.
    Solutions for Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
    Here you can find the meaning of Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer?, a detailed solution for Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer? has been provided alongside types of Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice Consider the data of a project. If the indirect cost per week is Rs.160. find the total cost after crashing two weeks?(A)9670(B)9690Correct answer is between ','. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
    Explore Courses for Mechanical Engineering exam

    Top Courses for Mechanical Engineering

    Explore Courses
    Signup for Free!
    Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
    10M+ students study on EduRev