Mechanical Engineering Exam  >  Mechanical Engineering Questions  >  If duration of activity f is changed to 10 da... Start Learning for Free
If duration of activity f is changed to 10 days, then the critical path for the project is
[2012]
  • a)
    Critical path remains the same and the total duration to complete the project changes to 19 days.
  • b)
    Critical path and the total duration to complete the project remains the same.
  • c)
    Critical path changes but the total duration to complete the project remains the same.
  • d)
    Critical path changes and the total duration to complete the project changes to 17 days.
Correct answer is option 'A'. Can you explain this answer?
Verified Answer
If duration of activity f is changed to 10 days, then the critical pat...
If duration of activity F has changed to 10 days, critical path remains the same and project duration will increase to 19 days.
View all questions of this test
Most Upvoted Answer
If duration of activity f is changed to 10 days, then the critical pat...
Explanation:
Critical path is the longest path in the network diagram which determines the minimum duration required to complete the project. Any change in the duration of an activity can affect the critical path of the project. The given question states that the duration of activity f is changed to 10 days and we need to determine the impact on the critical path and total duration of the project.

Impact on Critical Path:
To determine the impact on the critical path, we need to calculate the earliest start time (EST), earliest finish time (EFT), latest start time (LST), and latest finish time (LFT) for each activity in the network diagram. Using these values, we can calculate the total duration of the project and the critical path.

Before changing the duration of activity f:

Activity | Duration | Predecessor | EST | EFT | LST | LFT | Slack
------------|----------|-------------|-----|-----|-----|-----|------
A | 3 | | 0 | 3 | 0 | 3 | 0
B | 2 | A | 3 | 5 | 3 | 5 | 0
C | 5 | B | 5 | 10 | 5 | 10 | 0
D | 4 | C | 10 | 14 | 12 | 16 | 2
E | 2 | C | 10 | 12 | 10 | 12 | 0
F | 6 | D,E | 14 | 20 | 16 | 22 | 2

The critical path is A -> B -> C -> D -> F with a total duration of 20 days.

After changing the duration of activity f to 10 days:

Activity | Duration | Predecessor | EST | EFT | LST | LFT | Slack
------------|----------|-------------|-----|-----|-----|-----|------
A | 3 | | 0 | 3 | 0 | 3 | 0
B | 2 | A | 3 | 5 | 3 | 5 | 0
C | 5 | B | 5 | 10 | 5 | 10 | 0
D | 4 | C | 10 | 14 | 12 | 16 | 2
E | 2 | C | 10 | 12 | 10 | 12 | 0
F | 10 | D,E | 14 | 24 | 16 | 26 | 2

The critical path is A -> B -> C -> D -> F with a total duration of 19 days.

Conclusion:
Hence, we can see that the critical path remains the same but the total duration of the project changes to 19 days. This is because the change in duration of activity f has affected the EST and EFT of activity F, which has led to a change in the total duration of the project. However, the critical
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer?
Question Description
If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer?.
Solutions for If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer?, a detailed solution for If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer? has been provided alongside types of If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice If duration of activity f is changed to 10 days, then the critical path for the project is[2012]a)Critical path remains the same and the total duration to complete the project changes to 19 days.b)Critical path and the total duration to complete the project remains the same.c)Critical path changes but the total duration to complete the project remains the same.d)Critical path changes and the total duration to complete the project changes to 17 days.Correct answer is option 'A'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev