Mechanical Engineering Exam  >  Mechanical Engineering Questions  >   An R & D project has following activities to... Start Learning for Free
An R & D project has following activities to be performed. The time estimates are given in the table.
The number of days required to complete the project with a probability of 50% is __________
  • a)
    24
  • b)
    24
Correct answer is between ' 24, 24'. Can you explain this answer?
Verified Answer
An R & D project has following activities to be performed. The time e...
A‐ D‐ H = 6 + 2 + 10 = 18
A‐D‐G‐J = 6 +2 +5 +8 = 21
C‐ H = 9 + 10 = 19
C‐G‐J = 9+ 5+ 8 = 22
B‐ E‐ H = 4 + 7 + 10 = 21
B‐E‐G‐J = 4 + 7 + 5 + 8 = 24∗
B‐F‐I = 4+ 8+ 4 = 16
Expected completion time of the project itself gives the completion time of project with 50% probability.
μ = 24
View all questions of this test
Most Upvoted Answer
An R & D project has following activities to be performed. The time e...
A‐ D‐ H = 6 + 2 + 10 = 18
A‐D‐G‐J = 6 +2 +5 +8 = 21
C‐ H = 9 + 10 = 19
C‐G‐J = 9+ 5+ 8 = 22
B‐ E‐ H = 4 + 7 + 10 = 21
B‐E‐G‐J = 4 + 7 + 5 + 8 = 24∗
B‐F‐I = 4+ 8+ 4 = 16
Expected completion time of the project itself gives the completion time of project with 50% probability.
μ = 24
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Similar Mechanical Engineering Doubts

Top Courses for Mechanical Engineering

An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer?
Question Description
An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer?.
Solutions for An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer?, a detailed solution for An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer? has been provided alongside types of An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice An R & D project has following activities to be performed. The time estimates are given in the table.The number of days required to complete the project with a probability of 50% is __________a) 24b) 24Correct answer is between ' 24, 24'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev