Question Description
Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared
according to
the Mechanical Engineering exam syllabus. Information about Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam.
Find important definitions, questions, meanings, examples, exercises and tests below for Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer?.
Solutions for Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering.
Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of
Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer?, a detailed solution for Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer? has been provided alongside types of Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer? theory, EduRev gives you an
ample number of questions to practice Time estimates of an activity in a PERT network are to = 9 days; tp = 21 days; t,„ = 15 days. The approximate probability of completion of this activity in 14 days isa)16%b)34%c)50%d)84%Correct answer is option 'C'. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.