The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.
Ans. B
  • a)
    0.16
  • b)
    0.84
  • c)
    0.68
  • d)
    0.32
Correct answer is option ''. Can you explain this answer?
Verified Answer
The expected project completion time is found to be 34 days. The stan...
P = 0.84
View all questions of this test
Most Upvoted Answer
The expected project completion time is found to be 34 days. The stan...
Given data:
Expected project completion time (μ) = 34 days
Standard deviation (σ) = 5 days
Time taken to complete the project (X) = 39 days
To find: Probability of completing the project in 39 days (P(X ≤ 39))

Formula:
We can use the standard normal distribution formula to find the probability.
z = (X - μ) / σ
where z is the standard normal variable.

From the formula, we get:
z = (39 - 34) / 5 = 1

Using the z-table or calculator, we find that the probability of z ≤ 1 is 0.8413.

Therefore, the probability of completing the project in 39 days is:
P(X ≤ 39) = P(z ≤ 1) = 0.8413

Hence, the correct option is (b) 0.84.
Attention Mechanical Engineering Students!
To make sure you are not studying endlessly, EduRev has designed Mechanical Engineering study material, with Structured Courses, Videos, & Test Series. Plus get personalized analysis, doubt solving and improvement plans to achieve a great score in Mechanical Engineering.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer?
Question Description
The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer? for Mechanical Engineering 2024 is part of Mechanical Engineering preparation. The Question and answers have been prepared according to the Mechanical Engineering exam syllabus. Information about The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer? covers all topics & solutions for Mechanical Engineering 2024 Exam. Find important definitions, questions, meanings, examples, exercises and tests below for The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer?.
Solutions for The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer? in English & in Hindi are available as part of our courses for Mechanical Engineering. Download more important topics, notes, lectures and mock test series for Mechanical Engineering Exam by signing up for free.
Here you can find the meaning of The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer? defined & explained in the simplest way possible. Besides giving the explanation of The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer?, a detailed solution for The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer? has been provided alongside types of The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer? theory, EduRev gives you an ample number of questions to practice The expected project completion time is found to be 34 days. The standard deviation of the critical path is 5 days. Find the probability of completing the project in 39 days.Ans. Ba) 0.16b) 0.84c) 0.68d) 0.32Correct answer is option ''. Can you explain this answer? tests, examples and also practice Mechanical Engineering tests.
Explore Courses for Mechanical Engineering exam

Top Courses for Mechanical Engineering

Explore Courses
Signup for Free!
Signup to see your scores go up within 7 days! Learn & Practice with 1000+ FREE Notes, Videos & Tests.
10M+ students study on EduRev